Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A certain job was assigned to a group of women to do it in 20 days. But 12 women did not turn up for the job and the remaining did the job in 32 days. The original number of women in the group was?

A) 36 B) 32
C) 22 D) 28
 
Answer & Explanation Answer: B) 32

Explanation:

Let the total women in the group be 'W'

Then according to the given data,

 W x 20 = (W-12) x 32

 => W = 32 

Therefore, the total number of women in the group = 32

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

7 5329
Q:

X boys can do a piece of work in 24 days. In how much time (in days), 2X boys will do half of the work?

 

A) 6 B) 12
C) 18 D) 8
 
Answer & Explanation Answer: A) 6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 5328
Q:

Concept of Efficiency

A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?

Answer

A's 1 days work = 1/12 


B's 1 days work =1/6


Therefore, (A+B)'s 1 day's work= 1/12 + 1/6 = 1/4       


Therefore, Time taken by both to finish the whole work = 114 = 4 days


 


Alternatively :


Efficiency of A =100/12 =8.33%


Efficiency of B =100/6=16.66%


Combined efficiency of A and B both = 8.33+16.66=25%


Therefore, Time taken by both to finish the work (working together) =100/25= 4days

Report Error

View answer Workspace Report Error Discuss

Subject: Time and Work

3 5304
Q:

A and B together finish a wor in 20 days.They worked together for 15 days and then B left. Afer another 10 days,A finished the remaining work. In how many days A alone  can finish the job?

A) 30 B) 40
C) 50 D) 60
 
Answer & Explanation Answer: B) 40

Explanation:

(A+B)'s 15 days work = 120×15=34

Remaining work =  1/4

Now, 1/4 work is done by A in 10 days.

Whole work will be done by A in (10 x 4) = 40 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

6 4946
Q:

16 women can do a piece of work in 10 days while 15 men can do the same work in 12 days. All men and all women work alternately starting with all men, then find the time taken by them to complete the whole work?

A) 10 5/2 days B) 11 days
C) 11 2/5 days D) 12 1/2 days
 
Answer & Explanation Answer: A) 10 5/2 days

Explanation:

Let efficiency of every man and every woman be 'm' unit/day and 'w' unit/day respectively

15×12×m = 10×16×w

⇒ m/w = 8/9

Total work = 15 × 12 × 9 = 1620 units

In 2 days, total work done = 15 x 9 + 16 x 8 = 263 units

So, in 10 days work done will be = 263 × 5 = 1315 units

Remaining work will be done in = (1620-1315)/(15×8) = 5/2 days

Total days = 10 5/2 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

27 4908
Q:

50 men can build a tank in 40days, but though they begin the work together, 5 men quit every ten days. The time needed to build the tank is ?

A) 50 days B) 48 days
C) 47.5 days D) 49 days
 
Answer & Explanation Answer: A) 50 days

Explanation:

50 men can build a tank in 40 days 

Assume 1 man does 1 unit of work in 1 day

Then the total work is 50×40 = 2000 units

 

50 men work in the first 10 days and completes 50×10 = 500 units of work

45 men work in the next 10 days and completes 45×10 = 450 units of work

40 men work in the next 10 days and completes 40×10 = 400 units of work

35 men work in the next 10 days and completes 35×10 = 350 units of work

So far 500 + 450 + 400 + 350 = 1700 units of work is completed and

 

Remaining work is 2000 - 1700 = 300 units

 

30 men work in the next 10 days. In each day, they does 30 units of work.

 

Therefore, additional days required = 300/30 =10

 

Thus, total 10+10+10+10+10 = 50 days required.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams
Job Role: Bank PO , Bank Clerk

10 4814
Q:

Raghu can do a job in 12 days alone and Sam can do the same job in 15 days alone. A third person Aru whose efficiency is two-third of efficiency of both Ram and Shyam together, can do the same job in how many days alone?

A) 10 B) 12
C) 13 D) 15
 
Answer & Explanation Answer: A) 10

Explanation:

One day work of Raghu and Sam together = 1/12 + 1/15 = 9/60 = 3/20

Aru efficiency = 2/3 of (Raghu + Sam)

Number of days required for Aru to do thw work alone = 3/2 x 20/3 = 10 days. 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

9 4700
Q:

Application of Inverse Proportion

If 20 persons can do a piece of work in 7 days then calculate the number of persons require to complete the work in 28 days

Answer

Number of persons * days = work  


20 * 7 = 140 man- days 


 


Now,  x * 28  = 140 men- days


=> x =5         


Therefore in second case the required number of person is 5.


 


Second method:


Since work is constant, therefore  M1 x D1= M2 x D2


20 x 7 = M2 x 28


=> M2 = 5 


 

Report Error

View answer Workspace Report Error Discuss

Subject: Time and Work