Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

8 men can complete a work in 16 days. 16 women can complete the same work in 24 days. In how many days can 4 men and 8 women complete the same work?

A) B)
C) D)
 
Answer & Explanation Answer:

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

10 1401
Q:

Pavan and Sravan are two persons. If Pavan works with his actual efficiency and Sravan twice of his actual efficiency then it takes 25 days to complete the work. But If Pavan works twice of his actual efficiency and Sravan with his normal efficiency then the work is completed in 20 days. How many days would it take if Sravan alone works with his actual efficiency (in Days)?

A) 50 B) 100
C) 70 D) 35
 
Answer & Explanation Answer: B) 100

Explanation:

Let the Efficiency of pavan be E(P)

Let the Efficiency of sravan be E(S)

Here Work W = LCM(25,20) = 100

Now, E(P+2S) = 100/25 = 4 ....(1)

E(2P+S) = 100/20 = 5 ....(2)

Hence, from (1) & (2) we get

E(S) = 1

=> Number of days Savan alone work to complete the work  = 100/1 = 100 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

10 4550
Q:

Adam and Smith are working on a project. Adam takes 6 hrs to type 36 pages on a computer, while Smith takes 5 hrs to type 40 pages. How much time will they take, working together on two different computers to type a project of 120 pages?

A) 8 hrs 45 min B) 8 hrs 42 min
C) 8 hrs D) 8 hrs 34 min
 
Answer & Explanation Answer: D) 8 hrs 34 min

Explanation:

Number of pages typed by Adam in 1 hour = 36/6 = 6
Number of pages typed by Smith in 1 hour = 40/5 = 8
Number of pages typed by both in 1 hour = (6 + 8) = 14
Time taken by both to type 110 pages = (120 * 1/14) = 847 = 8 hrs 34 min.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams
Job Role: Bank PO , Bank Clerk

10 4108
Q:

9 women can complete a work in 50 days. If more 6 women were added to them, how many days before the work can be completed?

A) 30 B) 20
C) 15 D) 25
 
Answer & Explanation Answer: B) 20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

10 1059
Q:

P and Q can do a work in 4 hours and 12 hours respectively. P starts the work at 9am and they work alternately for one hour each. When will the work be completed ?

A) 3 am B) 12 pm
C) 1 pm D) 3 pm
 
Answer & Explanation Answer: D) 3 pm

Explanation:

Work done by P and Q in the first two hours, working alternately

= First hour P + Second hour Q

14+112=13

work is completed in 2 hours

Then, the total time required to complete the work by P and Q working alternately=2 x 3= 6hours

Thus, work will be completed at 3pm.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams
Job Role: Bank PO , Bank Clerk

10 6699
Q:

50 men can build a tank in 40days, but though they begin the work together, 5 men quit every ten days. The time needed to build the tank is ?

A) 50 days B) 48 days
C) 47.5 days D) 49 days
 
Answer & Explanation Answer: A) 50 days

Explanation:

50 men can build a tank in 40 days 

Assume 1 man does 1 unit of work in 1 day

Then the total work is 50×40 = 2000 units

 

50 men work in the first 10 days and completes 50×10 = 500 units of work

45 men work in the next 10 days and completes 45×10 = 450 units of work

40 men work in the next 10 days and completes 40×10 = 400 units of work

35 men work in the next 10 days and completes 35×10 = 350 units of work

So far 500 + 450 + 400 + 350 = 1700 units of work is completed and

 

Remaining work is 2000 - 1700 = 300 units

 

30 men work in the next 10 days. In each day, they does 30 units of work.

 

Therefore, additional days required = 300/30 =10

 

Thus, total 10+10+10+10+10 = 50 days required.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams
Job Role: Bank PO , Bank Clerk

10 5118
Q:

28 Men and 52 women working together completes a work in 22.5 days. 35 men and 65 women working together on same work will complete it in how many days?

A) 16 B) 18
C) 19 D) 21
 
Answer & Explanation Answer: B) 18

Explanation:

Clearly total persons are increased in  28/35 :: 52/65 = 4:5.

As time is inversely proportional to men, so total time will decrease in the ratio 5:4.

Hence, 22.5 x 4/5 = 18 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

10 4185
Q:

K can lay Highway road between two cities in 16 days. L can do the same job in 12 days. With the help of M, they completes the job in 4 days. How much days does it take for M alone to complete the work ?

A) 47/7 days B) 59/6 days
C) 48/5 days D) 57/5 days
 
Answer & Explanation Answer: C) 48/5 days

Explanation:

Amount of work K can do in 1 day = 1/16

Amount of work L can do in 1 day = 1/12

Amount of work K, L and M can together do in 1 day = 1/4

Amount of work M can do in 1 day = 1/4 - (1/16 + 1/12) = 3/16 – 1/12 = 5/48

=> Hence M can do the job on 48/5 days = 9 (3/5) days  

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE