Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A constructor estimates that 4 people can paint Mr. Karthik's house in 6 days. If he uses 5 people instead of 4, how long will they take to complete the job ?

A) 3 days B) 26/3 days
C) 13/4 days D) 24/5 days
 
Answer & Explanation Answer: D) 24/5 days

Explanation:

we know that m1 x d1 = m2 x d2
=> 4 x 6 = 5 x d
where d = no. of days taken by 5 men to paint
d = 24/5 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Analyst , Bank Clerk , Bank PO

5 3258
Q:

K can lay Highway road between two cities in 16 days. L can do the same job in 12 days. With the help of M, they completes the job in 4 days. How much days does it take for M alone to complete the work ?

A) 47/7 days B) 59/6 days
C) 48/5 days D) 57/5 days
 
Answer & Explanation Answer: C) 48/5 days

Explanation:

Amount of work K can do in 1 day = 1/16

Amount of work L can do in 1 day = 1/12

Amount of work K, L and M can together do in 1 day = 1/4

Amount of work M can do in 1 day = 1/4 - (1/16 + 1/12) = 3/16 – 1/12 = 5/48

=> Hence M can do the job on 48/5 days = 9 (3/5) days  

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

9 3243
Q:

A woman fills a bucket in 6 minutes. 1845 buckets have to be filled from 8 am. to 9:30 am. How many woman employees should be employed for this task?

A) 111 B) 117
C) 123 D) 139
 
Answer & Explanation Answer: C) 123

Explanation:

We know that, M1 × D1W1 = M2 × D2W2

Here M1 = 1, D1 = 6 min, W1 = 1 and M2 = M, D2 = 90 min, W2 = 1845

 

1 × 61 = M × 901845 

=> M = 123

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

8 3240
Q:

If 10 men take 15 days to complete a work. In how many days will 37 men complete the work?

A) 3 days B) 4 days
C) 5 days D) 6 days
 
Answer & Explanation Answer: B) 4 days

Explanation:

Given 10 men take 15 days to complete a work

=> Total mandays = 15 x 10 = 150

Let the work be 150 mandays.

=> Now 37 men can do 150 mandays in 150/37 =~ 4 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

15 3128
Q:

Lasya alone can do a work in 16 days. Srimukhi’s efficiency is 20 % lesser than that of Laya. If Rashmi and Srimukhi together can do the same work in 12 days, then find the efficiency ratio of Rashmi to that of Lasya?

A) 19 : 7 B) 30 : 19
C) 8 : 15 D) 31 : 17
 
Answer & Explanation Answer: C) 8 : 15

Explanation:

Given Lasya can do a work in 16 days.

 

Now, time taken by Srimukhi alone to complete the work = 16 x 100/80

 

Time taken by Rashmi = n days

 

=> (12 x 20)/(20 - 12) = (12 x 20)/n

 

=> n= 30 days.

 

Required ratio of efficiencies of Rashmi and Lasya = 1/30  ::  1/16  = 8 : 15.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

7 3115
Q:

K, L and M can do a piece of work in 20, 30 and 60 days respectively. In how many days can K do the total work if he is assisted by L and M on every third day ?

A) 15 days B) 13 days
C) 12 days D) 10 days
 
Answer & Explanation Answer: A) 15 days

Explanation:

In one day work done by K = 1/20

Work done by K in 2 days = 1/10

 

Work done by K,L,M on 3rd day =1/20 + 1/30 + 1/60 = 1/10

Therefore, workdone in 3 days is = 1/10 + 1/10 = 1/5

 

1/5th of the work will be completed at the end of 3 days.

The remaining work = 1 - 1/5 = 4/5

1/5 of work is completed in 3 days

Total work wiil be done in 3 x 5 = 15 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

3 3082
Q:

Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing 1/3 of the task. Then, Sharan takes over and completees the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayuk' had worked faster than Sharan ?

A) 24 B) 45
C) 72 D) 30
 
Answer & Explanation Answer: B) 45

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

16 3051
Q:

A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

A) 17 B) 19
C) 19.5 D) 21
 
Answer & Explanation Answer: B) 19

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 3034