Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Working 7 hours in a day, 4 men can do a piece of work in 8 days. Working 8 hours in a day, the required number of men to perform the same work in 4 days will be

A) 8 B) 4
C) 7 D) 9
 
Answer & Explanation Answer: C) 7

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 760
Q:

P can do (1/4)th of work in 10 days, Q can do 40% of work in 40 days and R can do (1/3)rd of work in 13 days. Who will complete the work first?

A) P B) Q
C) R D) Both P and R
 
Answer & Explanation Answer: C) R

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 2124
Q:

Three electronic devices make a beep after every 48 sec, 72 sec and 108 sec respectively. They beeped together at 10 a.m. The time when they will next make a beep together at the earliest is

A) 10:07:12 hrs B) 10:07:24 hrs
C) 10:07:36 hrs D) 10:07:48 hrs
 
Answer & Explanation Answer: A) 10:07:12 hrs

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 837
Q:

An hour-long test has 60 problems. If a student completes 30 problems in 25 minutes, then the required seconds he has taken on average for computing each of the remaining problems is

A) 70 seconds B) 50 seconds
C) 40 seconds D) 30 seconds
 
Answer & Explanation Answer: A) 70 seconds

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 659
Q:

A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?

A) 30 days B) 50 days
C) 40 days D) 60 days
 
Answer & Explanation Answer: C) 40 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 975
Q:

A can do as much work in 4 days as B can do in 5, and B can do as much work in 6 days as C in 7. In what time will C do a piece of work which A can do in a week ?

A) 10 5/24 days B) 4 4/5 days
C) 6 8/15 days D) 12 6/19 days
 
Answer & Explanation Answer: A) 10 5/24 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1163
Q:

Ramesh and Rahman can do a work in 20 and 25 days respectively. After doing collectively 10 days of work, they leave the work due to illness and Suresh completes rest of the work in 3 days. How many days Suresh alone can take to complete the whole work ?

A) 32 days B) 28 days
C) 29 days D) 30 days
 
Answer & Explanation Answer: D) 30 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 654
Q:

A and B can do a piece of work in 18 days, B and C in 24 days, A and C in 36 days. Working together they can do the work in

A) 12 days B) 13 days
C) 16 days D) 26 days
 
Answer & Explanation Answer: C) 16 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 689