Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A can do 50% of the job in 16 days, B can do 1/4th of the job in 24 days. In how many days can they do 3/4th of the job working together?

A) 24 B) 9
C) 21 D) 18
 
Answer & Explanation Answer: D) 18

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

17 2058
Q:

In a fort there was sufficient food for 200 soldiers for 31 days. After 27 days, 120 soldiers left the fort. For how many extra days will the rest of the food last for the remaining soldiers?

A) 12 days B) 10 days
C) 8 days D) 6 days
 
Answer & Explanation Answer: B) 10 days

Explanation:

Quantity of food = 200 X 31 = 6200 man-days

Till 27 days, quantity consumed = 27 X 200 = 5400 man-days

Remaining quantity = 6200 –5400 = 800 man days

Remaining soilders = 200 –120 = 80

Let remaining food will be sufficient for x days⇒5400 + 80x = 6200⇒x= 10 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2051
Q:

X and Y together can do a piece of work in 30 days. Y and Z together can do the work in 20 days. X starts the work and works for 15 days then Y takes that work and works for 27 days. Finally Z finishes the remaining work in 9 days. In how many days Y alone can complete the entire work?

 

A) 60 B) 45
C) 50 D) 65
 
Answer & Explanation Answer: A) 60

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1937
Q:

A and B can together do a piece of work in 10 days. If A works with twice of his efficiency and B works with an efficiency 1/3rd less than his efficiency, then the work gets completed in 6 days. In how many days can A and B do the work alone respectively?

A) 40/3, 40 B) 20/3, 20
C) 30, 20/3 D) 50/3, 25
 
Answer & Explanation Answer: A) 40/3, 40

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1936
Q:

48 people could complete a task in 17 days. After 6 days, 4 of the workers left. How many days from then will it take to complete the task?

A) 12 B) 13
C) 15 D) 16
 
Answer & Explanation Answer: A) 12

Explanation:

Given, 48 people can do a work in 17 days. So total work = 48 x 17 = 816
Work done by 48 people in 6 days = 288.

The remaining work = 816 - 288 = 528
After 6 days four workers left. So number of people working is 44
Total number of days required for 44 men to complete the remaining work = 528/44 = 12

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT

1 1909
Q:

A, B and C can complete a work in 10, 12 and 15 days respectively. All three of them starts together but after 2 days A leaves the job and B left the job 3 days before the work was completed. C completed the remaining work alone. In how many days was the total work completed?

A) 5 B) 6
C) 7 D) 8
 
Answer & Explanation Answer: C) 7

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1861
Q:

A & B together finish a job in 24 days, while A, B & C together can finish the same job in 8 days. C alone will finish the job in

A) 12 days B) 14 days
C) 16 days D) 24 days
 
Answer & Explanation Answer: A) 12 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

6 1847
Q:

A takes 24 day in completing a work alone. Time taken by A in completing 1/3rd of the work is equal to the time taken by B in completing half of the work. How many days will be taken in completing the work if both A & B start working together?

A) 21/3 days B) 48 days
C) 40 days D) 48/5 days
 
Answer & Explanation Answer: D) 48/5 days

Explanation:

Ans. 
Time taken by A to complete a work alone - 24 days
Time taken by A in completing 1/3 of work = 24*1/3= 8 Days
8 day = time taken by B in completing 1/2 of work
B alone can complete the work = 16 days
The required time in completing the work if both A & B start working together?
16*24 / 40 = 48/5 Days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work