FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A can do 1/3rd of a job in 3 days and B can do half of the job in 9 days. If they work on it together, then in how many days can they finish half of the job?

A) 4 B) 5
C) 6 D) 3
 
Answer & Explanation Answer: D) 3

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 849
Q:

A can do 75% of a job in 9 days and B can do half of the job in 8 days. If they work on it together, then in how many days can they do half of the job?

A) 40/7 B) 24/7
C) 7/2 D) 9/2
 
Answer & Explanation Answer: B) 24/7

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1118
Q:

A can paint a house in 25 days and B can do it in 10 days. Along with C, they did the job in 6.25 days only. Then in how many days, C alone can do the job?

A) 50 B) 40
C) 30 D) 60
 
Answer & Explanation Answer: A) 50

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1071
Q:

S and T can finish a work in 50 days. They worked together for 20 days and then left. How much of the work is left?

A) 3/5 B) 1/3
C) 1/2 D) 2/5
 
Answer & Explanation Answer: A) 3/5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 557
Q:

Concept of Efficiency

A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?

Answer

A's 1 days work = 1/12 


B's 1 days work =1/6


Therefore, (A+B)'s 1 day's work= 1/12 + 1/6 = 1/4       


Therefore, Time taken by both to finish the whole work = 114 = 4 days


 


Alternatively :


Efficiency of A =100/12 =8.33%


Efficiency of B =100/6=16.66%


Combined efficiency of A and B both = 8.33+16.66=25%


Therefore, Time taken by both to finish the work (working together) =100/25= 4days

Report Error

View answer Workspace Report Error Discuss

Subject: Time and Work

3 5419
Q:

S does half as much work as T in 1/7 of the time taken by T. If together they take 21 days to complete a work, then how may days shall S take to complete that work alone?

 

 

A) 26   B)  27  
C) 28   D) 32
 
Answer & Explanation Answer: B)  27  

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 524
Q:

P and Q undertook to do a work for Rs 7200. P alone could do it in 20 days and Q alone in 12 days. With the assistance of R they finished the work in 5days. What is the share (in Rs) of R?

 

A) 1800   B) 2400  
C) 2800   D) 2600
 
Answer & Explanation Answer: B) 2400  

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 410
Q:

70000 a year is how much an hour?

A) 80 B) 8
C) 0.8 D) 0.08
 
Answer & Explanation Answer: B) 8

Explanation:

Given for year = 70000

=> 365 days = 70000

=> 365 x 24 hours = 70000

=>   1 hour = ?

70000/365x24 = 7.990 = 8