Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work ?

A) 3 days B) 2 days
C) 6 days D) 12 days
 
Answer & Explanation Answer: C) 6 days

Explanation:

From the given data,

12 children 16 days work,
One child’s one day work = 1/192.


8 adults 12 days work,
One adult’s one day’s work = 1/96.


Work done in 3 days = ((1/96) x 16 x 3) = 1/2


Remaining work = 1 – 1/2 = 1/2


(6 adults+ 4 children)’s 1 day’s work = 6/96 + 4/192 = 1/12

1/12 work is done by them in 1 day.

1/2 work is done by them in 12 x (1/2) = 6 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: TOEFL , GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

11 11781
Q:

P, Q, and R can do a job in 12 days together.  If their efficiency of working be in the ratio 3 : 8 : 5, Find in what time Q can complete the same work alone?

A) 36 days B) 30 days
C) 24 days D) 22 days
 
Answer & Explanation Answer: A) 36 days

Explanation:

Given the ratio of efficiencies of P, Q & R are 3 : 8 : 5

Let the efficiencies of P, Q & R be 3x, 8x and 5x respectively

They can do work for 12 days.

=> Total work = 12 x 16x = 192x

 

Now, the required time taken by Q to complete the job alone = 162x8x = 24 days.

Report Error

View Answer Report Error Discuss

17 11547
Q:

P alone can complete a piece of work in 6 days. Work done by Q alone in one day is equal to one-third of the work done by P alone in one day. In how many days can the work be completed if P and Q work together  ?

A) 5 (2/3) B) 6 (3/4 )
C) 4 (1/2) D) 3
 
Answer & Explanation Answer: C) 4 (1/2)

Explanation:

Work done by P alone in one day = 1/6th of the total work done by Q alone in one day = 1/3(of that done by P in one day) = 1/3(1/6 of the total) = 1/18 of the total. 

 

Work done by P and Q, working together in one day = 1/6 + 1/18  = 4/18 = 2/9 

 

They would take 9/2 days = 4 (1/2) days to complete the work working together.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

9 11316
Q:

If 34 men completed 2/5th of a work in 8 days working 9 hours a day. How many more man should be engaged to finish the rest of the work in 6 days working 9 hours a day ? 

A) 101 men B) 112 men
C) 102 men D) 120 men
 
Answer & Explanation Answer: C) 102 men

Explanation:

From the above formula i.e (m1 x t1/w1) = (m2 x t2/w2)

so, [(34 x 8 x 9)/(2/5)] = [(M x 6 x 9)/(3/5)]

so, M = 136 men

 

Number of men to be added to finish the work = 136-34 = 102 men.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

13 11056
Q:

6 boys and 8 girls can do job in 10 days , 26 boys & 48 women do work in 2 days. Find time taken by 15 boys and 20 girls to do same work ?

A) 2 days B) 3 days
C) 4 days D) 5 days
 
Answer & Explanation Answer: C) 4 days

Explanation:

One day work of 6 boys and 8 girls is given as 6b + 8g = 1/10 -------->(I)

 


One day work of 26 boys and 48 women is given as 26b + 48w = 1/2 -------->(II)

 

Divide both sides by 2 in (I) and then multiply both sides by 5

Now we get, 15b + 20g = 1/4.

Therefore, 15 boys and 20 girls can do the same work in 4 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

13 10983
Q:

There are three boats B1, B2 and B3 working together they carry 60 people in each trip. One day an early morning B1 carried 50 people in few trips alone. When it stopped carrying the passengers B2 and B3 started carrying the people together. It took a total of 10 trips to carry 300 people by B1, B2 and B3. It is known that each day on an average 300 people cross the river using only one of the 3 boats B1, B2 and B3. How many trips it would take to B1, to carry 150 passengers alone?

A) 15 B) 30
C) 25 D) 10
 
Answer & Explanation Answer: A) 15

Explanation:

Combined efficiency of all the three boats = 60 passenger/trip 

 

Now, consider option(a)

 

15 trips and 150 passengers means efficiency  of B1 =  10 passenger/trip 

 

which means in carrying 50 passengers B1 must has taken 5 trips. So the rest trips equal to 5 (10-5 = 5) in which B2 and B3 together carried remaining 250 (300 - 50 = 250) Passengers.

 

Therefore the efficiency of B2 and B3 = 250/5 = 50 passenger/trip  

 

Since, the combined efficiency of B1, B2 and B3 is 60. Which is same as given in the first statement hence option(a) is correct.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

33 10944
Q:

A can build a wall in 16 days while B can destroy it in 8 days. A worked for 5 days. Then B joined with A for the next 2 days. Find in how many days could A build the remaining wall ?

A) 12 days B) 14 days
C) 13 days D) 16 days
 
Answer & Explanation Answer: C) 13 days

Explanation:

Now, Total work = LCM(16, 8) = 48

A's one day work = + 48/16 = + 3

B's one day work = - 48/8 = -6

Given A worked for 5 days to build the wall => 5 days work = 5 x 3 = + 15

2days B joined with A in working = 2(3 - 6) = - 6

Remaining Work of building wall = 48 - (15 - 6) = 39

Now this remaining work will be done by A in = 39/3 = 13 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

15 10810
Q:

Time taken by P alone to finish a work is 50% more than the time taken by P and Q together. Q is thrice as efficient as R. If Q and R together can complete the work in 22.5 days, then how many days will P alone take to complete the work ?

A) 17 days B) 11 days
C) 15 days D) 16 days
 
Answer & Explanation Answer: C) 15 days

Explanation:

We know that Time is inversely proportional to Efficiency

Here given time ratio of P & P+Q as

P/P+Q = 150/100 = 3:2

Efficiency ratio of P & Q as

P:Q = 2:1 ....(1)

Given Efficiency ratio of Q & R as

Q:R = 3:1 ....(2)

From (1) & (2), we get

P:Q:R = 6:3:1

P alone can finish the work in

22.5(3+1)/6 = 15 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

16 10734