Q:

Two boys and a girl can do a work in 5 days, while a boy and 2 girls can do it in 6 days. If the boy is paid at the rate of 28$ a week, what should be the wages of the girl a week ?

A) 24 $ B) 22 $
C) 16 $ D) 14 $

Answer:   C) 16 $



Explanation:

Let the 1 day work of a boy=b and a girl=g, then
2b + g = 1/5 ---(i) and
b + 2g = 1/6 ---(ii)
On solving (i) & (ii), b=7/90, g=2/45
As payment of work will be in proportion to capacity of work and a boy is paid $ 28/week,
so a girl will be paid 28x  = 16 $.

Q:

P is 30% more efficient than Q. How much time will they, working together, take to complete a job which P alone could have done in 23 days?

A) 16 days B) 13 days
C) 15 days D) 12 days
 
Answer & Explanation Answer: B) 13 days

Explanation:

Ratio of times taken by P & Q = 100 : 130 = 10:13

Let Q takes x days to do the work

Then, 10:13 :: 23:x

=> x = 23x13/10

=> x = 299/10

P's 1 day's work = 1/23

Q's 1 day's work = 10/299

(P+Q)'s 1 day's work = (1/23 + 10/299) = 23/299 = 1/13

Hence, P & Q together can complete the work in 13 days.

Report Error

View Answer Workspace Report Error Discuss

10 218
Q:

If 2 men and 3 women can do a piece of work in 8 days and 3 men and 2 women in 7 days. In how many days can the work be done by 5 men and 4 women working together?

A) 3 days B) 6 days
C) 4 days D) 2 days
 
Answer & Explanation Answer: C) 4 days

Explanation:

From the given data,

=> (2 M + 3W) 8 = (3M + 2W)7

=> 16M + 24W = 21M + 14 W

=> 10W = 5M

=> 2W = M

=> 14W × ? = 7W × 8

? = 4 days

Report Error

View Answer Workspace Report Error Discuss

11 288
Q:

28 Men and 52 women working together completes a work in 22.5 days. 35 men and 65 women working together on same work will complete it in how many days?

A) 16 B) 18
C) 19 D) 21
 
Answer & Explanation Answer: B) 18

Explanation:

clearly total persons are increased in => 28/35 :: 52/65 = 4:5

As time is inversely proportional to men, so total time will decrease in the ratio 5:4

Hence, 22.5 x 4/5 = 18 days.

Report Error

View Answer Workspace Report Error Discuss

6 154
Q:

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left?

A) 8/15 B) 7/9
C) 6/13 D) 4/11
 
Answer & Explanation Answer: A) 8/15

Explanation:
P's 1 day's work = 1  
15
Q's 1 day's work = 1  
20
(P + Q)'s 1 day's work = ( 1 + 1 ) = 7  
15 20 60
(P + Q)'s 4 day's work = ( 7 x 4 ) = 7  
60 15
Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15
Report Error

View Answer Workspace Report Error Discuss

7 210
Q:

X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

A) 1/3 B) 2/3
C) 1/6 D) 5/6
 
Answer & Explanation Answer: C) 1/6

Explanation:

Given X can do in 10 days

=> 1 day work of X = 1/10

Y can do in 15 days

=> 1 day work of Y = 1/15

1day work of (X + Y) = 1/10 + 1/15 = 1/6

Given they are hired for 5 days

=> 5 days work of (X + Y) = 5 x 1/6 = 5/6

Therefore, Unfinished work = 1 - 5/6 = 1/6 