Q:

A and  B can do  a piece of work in 30 days , while  B and C can do the same work in 24 days and C and A in 20 days . They all work together for 10 days when B and C leave. How many days more will A take to finish  the work?

A) 18 days B) 24 days
C) 30 days D) 36 days

Answer:   A) 18 days



Explanation:

2(A+B+C)'s 1 day work = \inline {\color{Black}\left ( \frac{1}{30}+\frac{1}{24}+\frac{1}{20} \right )=\frac{15}{120}=\frac{1}{8} }

=>(A+B+C)'s  1 day's work=\inline {\color{Black}\frac{1}{16} }

work done by A,B and C in 10 days=\inline {\color{Black}\frac{10}{16}= \frac{5}{8}}

Remaining work=\inline {\color{Black}(1-\frac{5}{8})= \frac{3}{8}}

A's 1 day's work =\inline {\color{Black}(\frac{1}{16}-\frac{1}{24})=\frac{1}{48}}

Now, \inline {\color{Black}\frac{1}{48}} work is done by A in 1 day.

So, \inline {\color{Black}\frac{3}{8}} work  wil be done by A in \inline {\color{Black}(48\times \frac{3}{8})} = 18 days

Q:

A contractor undertake to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged so that the work may finish in time ? 

A) 64 B) 62
C) 58 D) 56
 
Answer & Explanation Answer: D) 56

Explanation:

Days remaining 124 – 64 = 60 days

Remaining work = 1 - 2/3 = 1/3

Let men required men for working remaining days be 'm'

So men required = (120 x 64)/2 = (m x 60)/1 => m = 64

Men discharge = 120 – 64 = 56 men.

Report Error

View Answer Workspace Report Error Discuss

4 70
Q:

A can build a wall in 16 days while B can destroy it in 8 days. A worked for 5 days. Then B joined with A for the next 2 days. Find in how many days could A build the remaining wall ?

A) 12 days B) 14 days
C) 13 days D) 16 days
 
Answer & Explanation Answer: C) 13 days

Explanation:

Now, Total work = LCM(16, 8) = 48

A's one day work = + 48/16 = + 3

B's one day work = - 48/8 = -6

Given A worked for 5 days to build the wall => 5 days work = 5 x 3 = + 15

2days B joined with A in working = 2(3 - 6) = - 6

Remaining Work of building wall = 48 - (15 - 6) = 39

Now this remaining work will be done by A in = 39/3 = 13 days.

Report Error

View Answer Workspace Report Error Discuss

7 119
Q:

A mother can do a certain job in x hours. Her daughter takes twice as long to do the job. Working together, they can do the job in 6 hours. How many hours does the mother take to do the job ?

A) 3 B) 6
C) 9 D) 12
 
Answer & Explanation Answer: C) 9

Explanation:

The mother completes the job in x hours.
So, the daughter will take 2x hours to complete the same job.

 

In an hour, the mother will complete 1/x of the total job.
In an hour, the daughter will complete 1/2x of the total job.

 

So, if the mother and daughter work together, in an hour they will complete 1/x + 1/2x of the job.
i.e., in an hour they will complete 3/2x of the job.

 

The question states that they complete the entire task in 6 hours if they work together.
i.e., they complete 1/6 th of the task in an hour.

 

Equating the two information, we get 3/2x = 1/6
By solving for x, we get 2x = 18 or x = 9.

 

The mother takes 9 hours to complete the job.

Report Error

View Answer Workspace Report Error Discuss

8 220
Q:

K can lay Highway road between two cities in 16 days. L can do the same job in 12 days. With the help of M, they completes the job in 4 days. How much days does it take for M alone to complete the work ?

A) 47/7 days B) 59/6 days
C) 48/5 days D) 57/5 days
 
Answer & Explanation Answer: C) 48/5 days

Explanation:

Amount of work K can do in 1 day = 1/16

Amount of work L can do in 1 day = 1/12

Amount of work K, L and M can together do in 1 day = 1/4

Amount of work M can do in 1 day = 1/4 - (1/16 + 1/12) = 3/16 – 1/12 = 5/48

=> Hence M can do the job on 48/5 days = 9 (3/5) days  

Report Error

View Answer Workspace Report Error Discuss

6 154
Q:

After working for 8 days, Hari Ram finds that only 1/3 rd of the work has been done. He employs Satya who is 60% as efficient as Hari Ram. How many days more would Satya take to complete the work ?

A) 24 1/2 days B) 25 3/2 days
C) 24 2/3 days D) 26 2/3 days
 
Answer & Explanation Answer: D) 26 2/3 days

Explanation:

1/3 ---- 8

1 -------?
Hari can do total work in = 24 days

As satya is 60% efficient as Hari, then

Satya = 1/24 x 60/100 = 1/40

=> Satya can do total work in 40 days

1 ----- 40

2/3 ---- ? => 26 2/3 days.