3
Q:

A single reservoir supplies the petrol to the whole city, while the reservoir is fed by a single pipeline filling the reservoir with the stream of uniform volume. When the reservoir is full and if 40,000 liters of petrol is used daily, the suply fails in 90 days.If 32,000 liters of petrol is used daily, it fails in 60 days. How much petrol can be used daily with out the supply ever failing? 

A) 64000 liters B) 56000 liters
C) 78000 liters D) 60000 liters

Answer:   B) 56000 liters



Explanation:

Let x liter be the per day filling and v litr be the capacity of the reservoir, then 

      90x + v = 40000 * 90     -----(1)

      60x + v= 32000 * 60     ------(2)

solving eq.(1) and (2) , we get

      x = 56000

Hence , 56000 liters per day can be used without the failure of supply.

Q:

P is 30% more efficient than Q. How much time will they, working together, take to complete a job which P alone could have done in 23 days?

A) 16 days B) 13 days
C) 15 days D) 12 days
 
Answer & Explanation Answer: B) 13 days

Explanation:

Ratio of times taken by P & Q = 100 : 130 = 10:13

Let Q takes x days to do the work

Then, 10:13 :: 23:x

=> x = 23x13/10

=> x = 299/10

P's 1 day's work = 1/23

Q's 1 day's work = 10/299

(P+Q)'s 1 day's work = (1/23 + 10/299) = 23/299 = 1/13

Hence, P & Q together can complete the work in 13 days.

Report Error

View Answer Workspace Report Error Discuss

10 218
Q:

If 2 men and 3 women can do a piece of work in 8 days and 3 men and 2 women in 7 days. In how many days can the work be done by 5 men and 4 women working together?

A) 3 days B) 6 days
C) 4 days D) 2 days
 
Answer & Explanation Answer: C) 4 days

Explanation:

From the given data,

=> (2 M + 3W) 8 = (3M + 2W)7

=> 16M + 24W = 21M + 14 W

=> 10W = 5M

=> 2W = M

=> 14W × ? = 7W × 8

? = 4 days

Report Error

View Answer Workspace Report Error Discuss

11 288
Q:

28 Men and 52 women working together completes a work in 22.5 days. 35 men and 65 women working together on same work will complete it in how many days?

A) 16 B) 18
C) 19 D) 21
 
Answer & Explanation Answer: B) 18

Explanation:

clearly total persons are increased in => 28/35 :: 52/65 = 4:5

As time is inversely proportional to men, so total time will decrease in the ratio 5:4

Hence, 22.5 x 4/5 = 18 days.

Report Error

View Answer Workspace Report Error Discuss

6 154
Q:

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left?

A) 8/15 B) 7/9
C) 6/13 D) 4/11
 
Answer & Explanation Answer: A) 8/15

Explanation:
P's 1 day's work = 1  
15
Q's 1 day's work = 1  
20
(P + Q)'s 1 day's work = ( 1 + 1 ) = 7  
15 20 60
(P + Q)'s 4 day's work = ( 7 x 4 ) = 7  
60 15
Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15
Report Error

View Answer Workspace Report Error Discuss

7 210
Q:

X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

A) 1/3 B) 2/3
C) 1/6 D) 5/6
 
Answer & Explanation Answer: C) 1/6

Explanation:

Given X can do in 10 days

=> 1 day work of X = 1/10

Y can do in 15 days

=> 1 day work of Y = 1/15

1day work of (X + Y) = 1/10 + 1/15 = 1/6

Given they are hired for 5 days

=> 5 days work of (X + Y) = 5 x 1/6 = 5/6

Therefore, Unfinished work = 1 - 5/6 = 1/6 

Report Error

View Answer Workspace Report Error Discuss

8 354