Q:

A contractor  undertook a project to complete it in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that  he needed to increase 5 additional  men every 2 days to complete the work in the time the client wanted it:

If the work was further increased by 50% but the contractor continues to increase the 5 workers o every 2 days then how many more days are required over the initial time specified by the  client.

A) 1 day B) 2 days
C) 5 days D) None of these

Answer:   B) 2 days



Explanation:

Total work = 100+50 = 150man-days

In 8 days 100 man-days work  has been completed. Now on 9th and 10th day there will be 25 workers. So in 2 days they wll complete additional 50 man- days work. Thus the work requires 2 more days.

Q:

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left?

A) 8/15 B) 7/9
C) 6/13 D) 4/11
 
Answer & Explanation Answer: A) 8/15

Explanation:
P's 1 day's work = 1  
15
Q's 1 day's work = 1  
20
(P + Q)'s 1 day's work = ( 1 + 1 ) = 7  
15 20 60
(P + Q)'s 4 day's work = ( 7 x 4 ) = 7  
60 15
Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15
Report Error

View Answer Workspace Report Error Discuss

1 15
Q:

X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

A) 1/3 B) 2/3
C) 1/6 D) 5/6
 
Answer & Explanation Answer: C) 1/6

Explanation:

Given X can do in 10 days

=> 1 day work of X = 1/10

Y can do in 15 days

=> 1 day work of Y = 1/15

1day work of (X + Y) = 1/10 + 1/15 = 1/6

Given they are hired for 5 days

=> 5 days work of (X + Y) = 5 x 1/6 = 5/6

Therefore, Unfinished work = 1 - 5/6 = 1/6 

Report Error

View Answer Workspace Report Error Discuss

8 248
Q:

If 10 men take 15 days to complete a work. In how many days will 37 men complete the work?

A) 3 days B) 4 days
C) 5 days D) 6 days
 
Answer & Explanation Answer: B) 4 days

Explanation:

Given 10 men take 15 days to complete a work

=> Total mandays = 15 x 10 = 150

Let the work be 150 mandays.

=> Now 37 men can do 150 mandays in 150/37 =~ 4 days

Report Error

View Answer Workspace Report Error Discuss

12 187
Q:

Three taps P, Q and R can fill a tank in 12 hrs, 15 hrs and 20 hrs respectively. If P is open all the time and Q and R are open for one hour each alternately, starting with Q, then the tank will be full in how many hours ?

A) 9 hrs B) 7 hrs
C) 13 hrs D) 11 hrs
 
Answer & Explanation Answer: B) 7 hrs

Explanation:

Given,

P can fill in 12 hrs

Q can fill in 15 hrs

R can fill in 20 hrs

=> Volume of tank = LCM of 12, 15, 20 = 60 lit

=> P alone can fill the tank in 60/12 = 5 hrs

=> Q alone can fill the tank in 60/15 = 4 hrs

=> R alone can fill the tank in 60/20 = 3 hrs

Tank can be filled in the way that

(P+Q) + (P+R) + (P+Q) + (P+R) + ....

=> Tank filled in 2 hrs = (5+4) + (5+3) = 9 + 8 = 17 lit

=> In 6 hrs = 17 x 6/2 = 51 lit

=> In 7th hr = 51 + (5+4) = 51 + 9 = 60 lit

=> So, total tank will be filled in 7 hrs.

Report Error

View Answer Workspace Report Error Discuss

7 366
Q:

P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?

A) 56 days B) 54 days
C) 60 days D) 64 days
 
Answer & Explanation Answer: D) 64 days

Explanation:

(P+Q)'s 1 day work = 1/24

P's 1 day work = 1/32

=> Q's 1 day work = 1/24 - 1/32 = 1/96

Work done by (P+Q) in 8 days = 8/24 = 1/3

Remainining work = 1 - 1/3 = 2/3

Time taken by Q to complete the remaining work = 2/3 x 96 = 64 days.

Report Error

View Answer Workspace Report Error Discuss