6
Q:

A contractor undertakes to complete a work in 130 days. He employs 150 men for 25 days and they complete 1/4 of the work . He then reduces the number of men to 100, who work for 60 days, after which there are 10 days holidays.How many men must be employed for the remaining period to finish the work? 

Answer:
Q:

Sixty men can stitch 150 shirts in 30 days working 8 hours a day. In how many days can 35 men stitch 200 shirts working 6 hours a day ?

A) 87.5 B) 89
C) 91.5 D) 93.5
 
Answer & Explanation Answer: C) 91.5

Explanation:

We have M1 D1 H1 / W1 = M2 D2 H2 / W2 (Variation rule)
(60 x 30 x 8)/ 150 = (35 x D2 x 6) / 200
D2 = (60 x 30 x 8 x 200) / (150 x 35 x 6) => D2 = 91.42 days =~ 91.5 days.

Report Error

View Answer Workspace Report Error Discuss

1 12
Q:

A can complete a piece of work in 12 days and B is 60% more efficient than A. In how many days B will complete the same work  ?

A) 8.7 hrs B) 5.2 hrs
C) 5 hrs D) 7.5 hrs
 
Answer & Explanation Answer: D) 7.5 hrs

Explanation:

Ratio of times taken by A and B = 160 : 100
A can do the work in 12 days
Let B can do the work in "D" days
=> 160:100 = 12 : D
=> D = 12 x 100/160 = 7.5 hrs

Report Error

View Answer Workspace Report Error Discuss

2 45
Q:

A can finish a work in 18 days and B can do the same work in half the time taken by A. then, working together, what part of the same work they can finish in a day ?

A) Total work B) One-fourth work
C) Half work D) Two-third work
 
Answer & Explanation Answer: C) Half work

Explanation:

A can do the work = 18 days
B can do the work = 18/2 = 9 days
(A + B)'s 1 day work = 1/18 + 1/9 = 1/6
=> In 3 days = 3x1/6 = 1/2 work is completed.

Report Error

View Answer Workspace Report Error Discuss

1 35
Q:

10 boys can complete a work in 7 days and 10 girls take 14 days to complete the work. How many days will 5 boys and 10 girls take to complete the work ?

A) 13 days B) 10 days
C) 7 days D) 16 days
 
Answer & Explanation Answer: C) 7 days

Explanation:

1 boy's 1 day work = 1/70
1 girl's 1 day work = 1/140
(5 boys + 10 girls)'s 1 day work
= (5/70 + 10/140) = (1/14 + 1/14) = 1/7

5 boys and 10 girls will complete the work in 7 days.

Report Error

View Answer Workspace Report Error Discuss

2 49
Q:

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days  ?

A) 9 days B) 11 days
C) 13 days D) 15 days
 
Answer & Explanation Answer: C) 13 days

Explanation:

Ratio of times taken by A and B = 100 : 130 = 10 : 13.
Suppose B takes x days to do the work.

Then, 10 : 13 :: 23 : x     =>     x = ( 23 x 13/10 )     =>     x = 299 /10.

A's 1 day's work = 1/23 ;
B's 1 day's work = 10/299 .

(A + B)'s 1 day's work = ( 1/23 + 10/299 ) = 23/299 = 113 .

Therefore, A and B together can complete the work in 13 days. 

Report Error

View Answer Workspace Report Error Discuss

1 60