8
Q:

Adam and Smith are working on a project. Adam takes 6 hrs to type 36 pages on a computer, while Smith takes 5 hrs to type 40 pages. How much time will they take, working together on two different computers to type a project of 120 pages?

A) 8 hrs 45 min B) 8 hrs 42 min
C) 8 hrs D) 8 hrs 34 min

Answer:   D) 8 hrs 34 min

Explanation:

Number of pages typed by Adam in 1 hour =  = 6
Number of pages typed by Smith in 1 hour =  = 8
Number of pages typed by both in 1 hour = (6 + 8) = 14
Time taken by both to type 110 pages = (120 * 1/14) = 8  = 8 hrs 34 min.

Q:

K can build a wall in 30 days. L can demolish that wall in 60 days. If K and L work on alternate days, when will the wall be completed ?

A) 120 days B) 119 days
C) 118 days D) 117 days
 
Answer & Explanation Answer: D) 117 days

Explanation:

K's work in a day(1st day) = 1/30
L's work in a day(2nd day)= -1/60(demolishing)
hence in 2 days, combined work= 1/30 - 1/60
=1/60
since both works alternatively, K will work in odd days and L will work in even days.
1/60 unit work is done in 2 days
58/60 unit work will be done in 2 x 58 days = 116 days
Remaining work = 1-58/60
= 2/60
= 1/30
Next day, it will be K's turn and K will finish the remaining 1/30 work.
hence total days = 116 + 1 = 117.

Report Error

View Answer Workspace Report Error Discuss

5 161
Q:

A contractor undertook to complete a piece of work in 120 Days and employed 140 men upon it. At the end of 66 days only half of the work was done,so he put on 25 extra men. By how much time did he exceed the specific time ?

A) 2 days B) 3 days
C) 4 days D) 5 days
 
Answer & Explanation Answer: A) 2 days

Explanation:

work done=total number of person x number of days;
half of work done = 140 x 66;
For half of remaining work 25 extra men are added.
Therefore, total men for half work remaining = 140 + 25 = 165;
Let 2nd half work will be completed in K days;
140 x 66 = 165 x K
K = 122;
Hence, extra days => 122-120 = 2days.

Report Error

View Answer Workspace Report Error Discuss

1 193
Q:

A,B,C together can do a piece of work in 10 days.All the three started workingat it together and after 4 days,A left.Then,B and C together completed the work in 10 more days.In how many days can complete a work alone ?

A) 25 B) 24
C) 23 D) 21
 
Answer & Explanation Answer: A) 25

Explanation:

(A+B+C) do 1 work in 10 days.
So (A+B+C)'s 1 day work=1/10 and as they work together for 4 days so workdone by them in 4 days=4/10=2/5
Remaining work=1-2/5=3/5
(B+C) take 10 more days to complete 3/5 work.
So( B+C)'s 1 day work=3/50
Now A'S 1 day work=(A+B+C)'s 1 day work-(B+C)'s 1 day work=1/10-3/50=1/25
A does 1/25 work in in 1 day
Therefore 1 work in 25 days.

Report Error

View Answer Workspace Report Error Discuss

2 122
Q:

A can write 32 pages in 6 hours and B can write 40 pages in 5 hours. If they write together, in how many hours they can write 110 pages ?

A) 7 hrs B) 6 hrs 10 min
C) 5 hrs 25min D) 8 hrs 15 min
 
Answer & Explanation Answer: D) 8 hrs 15 min

Explanation:

A can write in 1hour = 32/6 pages
similarly
B in 1 hour = 40/5 pages

Together (A+B) in 1 hour = 32/6 + 40/5 = 40/3
so,
A+B write 40/3 pages in 1 hour
A+B write 110 pages in (3/40) x 110 Hours = 8 hours 15 min.

Report Error

View Answer Workspace Report Error Discuss

2 258
Q:

There is sufficient salary to give K for 10 days and L for 15 days. Then how many days will the money last if both has to be given the salary ?

A) 6 days B) 12 days
C) 4 days D) 9 days
 
Answer & Explanation Answer: A) 6 days

Explanation:

K's 1 day's salary = 1/10
L's 1 day's salary = 1/15
Together their 1 day's salary = 1/10 + 1/15
= 3/30 + 2/30
= 5/30
= 1/6
So the money will be
enough for paying them both for 6 days.

Report Error

View Answer Workspace Report Error Discuss

1 114