6
Q:

Amit can do a piece of work in 45 days, but Bharath can do the same work in 5 days less, than Amit, when  working alone. Amit and Bharath both started the work together but Bharath  left after some days and Amit finished the remaining work in 56 days with half of his efficiency but he did the work with Bharath with his complete efficiency. For how many days they had worked together?

A) 6 B) 8
C) 9 D) 12

Answer:   B) 8



Explanation:

    

Amit did the work in 56 days = 

 Rest work  was done by Amit and Bharath =  = 8 days

( since Amit and Bharath  do the work in one day = )

Q:

X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

A) 1/3 B) 2/3
C) 1/6 D) 5/6
 
Answer & Explanation Answer: C) 1/6

Explanation:

Given X can do in 10 days

=> 1 day work of X = 1/10

Y can do in 15 days

=> 1 day work of Y = 1/15

1day work of (X + Y) = 1/10 + 1/15 = 1/6

Given they are hired for 5 days

=> 5 days work of (X + Y) = 5 x 1/6 = 5/6

Therefore, Unfinished work = 1 - 5/6 = 1/6 

Report Error

View Answer Workspace Report Error Discuss

8 241
Q:

If 10 men take 15 days to complete a work. In how many days will 37 men complete the work?

A) 3 days B) 4 days
C) 5 days D) 6 days
 
Answer & Explanation Answer: B) 4 days

Explanation:

Given 10 men take 15 days to complete a work

=> Total mandays = 15 x 10 = 150

Let the work be 150 mandays.

=> Now 37 men can do 150 mandays in 150/37 =~ 4 days

Report Error

View Answer Workspace Report Error Discuss

11 169
Q:

Three taps P, Q and R can fill a tank in 12 hrs, 15 hrs and 20 hrs respectively. If P is open all the time and Q and R are open for one hour each alternately, starting with Q, then the tank will be full in how many hours ?

A) 9 hrs B) 7 hrs
C) 13 hrs D) 11 hrs
 
Answer & Explanation Answer: B) 7 hrs

Explanation:

Given,

P can fill in 12 hrs

Q can fill in 15 hrs

R can fill in 20 hrs

=> Volume of tank = LCM of 12, 15, 20 = 60 lit

=> P alone can fill the tank in 60/12 = 5 hrs

=> Q alone can fill the tank in 60/15 = 4 hrs

=> R alone can fill the tank in 60/20 = 3 hrs

Tank can be filled in the way that

(P+Q) + (P+R) + (P+Q) + (P+R) + ....

=> Tank filled in 2 hrs = (5+4) + (5+3) = 9 + 8 = 17 lit

=> In 6 hrs = 17 x 6/2 = 51 lit

=> In 7th hr = 51 + (5+4) = 51 + 9 = 60 lit

=> So, total tank will be filled in 7 hrs.

Report Error

View Answer Workspace Report Error Discuss

7 356
Q:

P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?

A) 56 days B) 54 days
C) 60 days D) 64 days
 
Answer & Explanation Answer: D) 64 days

Explanation:

(P+Q)'s 1 day work = 1/24

P's 1 day work = 1/32

=> Q's 1 day work = 1/24 - 1/32 = 1/96

Work done by (P+Q) in 8 days = 8/24 = 1/3

Remainining work = 1 - 1/3 = 2/3

Time taken by Q to complete the remaining work = 2/3 x 96 = 64 days.

Report Error

View Answer Workspace Report Error Discuss

6 329
Q:

A can complete 9/10 part of a work in 31 days. After that, with the help of B he can complete the remaining work in 4 days. In how many days will  A and B together can complete that work ?

A) 36 B) 40
C) 42 D) 38
 
Answer & Explanation Answer: B) 40

Explanation:

Remaining work = 1 - 9/10 = 1/10

=> A & B together completes 1/10 of work in 4 days

=> 1 work can completed in ------ ? days

Let it be x days

=>  

=> x = 40 days.

Hence, A & B together can complete the work in 40 days.

Report Error

View Answer Workspace Report Error Discuss

6 166