1
Q:

Kaushalya can do a work in 20 days, while kaikeyi can do the same work in 25 days. They started the work jointly.Few days later Sumitra also joined them and thus all of them completed the whole work in 10 days. All of them were paid total Rs.700. What is the Share of Sumitra?

A) Rs.130 B) Rs.185
C) Rs.70 D) can't be determined

Answer:   C) Rs.70

Explanation:

Efficiency of kaushalya = 5%

Efficiency of kaikeyi  = 4%

Thus, in 10 days working together they will complete only 90% of the work.

          [(5+4)*10] =90

Hence, the remaining work will surely done by sumitra, which is 10%.

Thus, sumitra will get 10% of Rs. 700, which is Rs.70

Q:

A group of men can complete a job in K hours. After every 4 hours, half the number of men working at that point of time leave the job. Continuing this way if the job is finished in 16 hours, what is the value of K ?

A) 7 hrs B) 7.5 hrs
C) 8 hrs D) 8.25 hrs
 
Answer & Explanation Answer: B) 7.5 hrs

Explanation:

Let there are L men

job requires LK man hours.

job completed in first 4 hrs = Lx4 = 4L
job completed in next 4 hrs = 4xL/2 = 2L
job completed in next 4 hrs = 4xL/4 = L
job completed in last 4 hrs = 4xL/8 = L/2
4L + 2L + L + L/2 = KL
K = 7+1/2 = 7.5 hours.

Report Error

View Answer Workspace Report Error Discuss

1 13
Q:

A can do a work in 9 days, B can do a work in 7 days, C can do a work in 5 days. A works on the first day, B works on the second day and C on the third day respectively that is they work on alternate days. When will they finish the work ?

A) [7 + (215/345)] days B) [6 + (11/215)] days
C) [6 + (261/315)] days D) [5 + (112/351)] days
 
Answer & Explanation Answer: C) [6 + (261/315)] days

Explanation:

After day 1, A finishes 1/9 of the work.

After day 2, B finishes 1/7 more of the total work. (1/9) + (1/7) is finished.

After day 3, C finishes 1/5 more of total work. Total finished is 143/315.

So, after day 6, total work finished is 286/315.

Now remaining work = 315 - 286 = 29 /315

On day 7, A will work again

Work will be completed on day 7 when A is working. He must finish 29/315 of total remaining work.

Since he takes 9 days to finish the total task, he will need 261/315 of the day.

Total days required is 6 + (261/315) days.

Report Error

View Answer Workspace Report Error Discuss

3 28
Q:

One girl can eat 112 chocolates in half a minute, and her boy friend can eat half as many in twice the length of time. How many chocolates can both boy and girl eat in 12 seconds ?

A) 44 B) 32
C) 56 D) 49
 
Answer & Explanation Answer: C) 56

Explanation:

Girl eats 112 chocolates in 30 sec
so she can eat in 12 sec is 12 x 112/30 = 44.8 chocolates.

Her boy friend can eat one-half of 112 in twice of 30 sec
so he can eat 56 in 60 sec
Then he can eat in 12 sec is 56 x 12/60 = 11.2 chocolates.

Hence, together they can eat
=> 44.8 + 11.2
56 chocolates in 12 seconds.

Report Error

View Answer Workspace Report Error Discuss

5 16
Q:

Two boys and a girl can do a work in 5 days, while a boy and 2 girls can do it in 6 days. If the boy is paid at the rate of 28$ a week, what should be the wages of the girl a week ?

A) 24 $ B) 22 $
C) 16 $ D) 14 $
 
Answer & Explanation Answer: C) 16 $

Explanation:

Let the 1 day work of a boy=b and a girl=g, then
2b + g = 1/5 ---(i) and
b + 2g = 1/6 ---(ii)
On solving (i) & (ii), b=7/90, g=2/45
As payment of work will be in proportion to capacity of work and a boy is paid $ 28/week,
so a girl will be paid 28x  = 16 $.

Report Error

View Answer Workspace Report Error Discuss

3 14
Q:

A constructor estimates that 4 people can paint Mr. Karthik's house in 6 days. If he uses 5 people instead of 4, how long will they take to complete the job ?

A) 3 days B) 26/3 days
C) 13/4 days D) 24/5 days
 
Answer & Explanation Answer: D) 24/5 days

Explanation:

we know that m1 x d1 = m2 x d2
=> 4 x 6 = 5 x d
where d = no. of days taken by 5 men to paint
d = 24/5 days.

Report Error

View Answer Workspace Report Error Discuss

4 19