12
Q:

Two pipes A and B can fill a tank in 24 hours and  hours respectively. Harihar opened the pipes A and B to fill an empty tank and some times later he closed the taps A and B , when the tank was supposed to be full. After that it was found that the tank was emptied in 2.5 hours because an outlet pipe "C" connected to the tank was open from the beginning. If Harihar closed the pipe C instead of closing pipes A and B the remaining tank would have been filled in :

A) 2 hours B) 8 hours
C) 6 hours D) 4 hours

Answer:   B) 8 hours



Explanation:

Efficiency of Inlet pipe A = 4.16%                              

Efficiency of Inlet pipe B = 5.83%                              

 Efficiency of A and B together = 100 %  

Now, if the efficiency of outlet pipe be x% then in 10 hours the capacity of tank which will be filled = 10 *  (10 - x)

Now, since this amount of water is being emptied by C at x% per hour, then            

           x = 8%

Therefore, in 10 hours 20% tank is filled only. Hence, the remaining 80% of the  capacity will be filled by pipes A and B  in 80/10 = 8 hours 

Q:

Amar can do a piece of work in 10 days. He works at it for 4 days and then Arun finishes it in 9 days. In how many days can Amar and Arun together finish the work ?

A) 4 days B) 8 days
C) 3 days D) 6 days
 
Answer & Explanation Answer: D) 6 days

Explanation:

4/10 + 9/x = 1

=> x = 15

Then both can do in

1/10 + 1/15 = 1/6

=> 6 days

Report Error

View Answer Workspace Report Error Discuss

2 39
Q:

12 men complete a work in 9 days. After they have worked for 6 days, 4 more men join them. How many days will they take to complete the remaining work ?

A) 2 days B) 2.5 days
C) 2.25 days D) 3 days
 
Answer & Explanation Answer: C) 2.25 days

Explanation:

1 man's 1 day work = 1/108
12 men's 6 day's work = 1/9 x 6 = 2/3

Remaining work = 1 - 2/3 = 1/3

16 men's 1 day work = 1/108 x 16 = 4/27
4/27 work is done by them in 1 day.

1/3 work is done by them in 27/4 x 1/3 = 9/4 days.

Report Error

View Answer Workspace Report Error Discuss

2 98
Q:

P alone can complete a piece of work in 6 days. Work done by Q alone in one day is equal to one-third of the work done by P alone in one day. In how many days can the work be completed if P and Q work together  ?

A) 5 (2/3) B) 6 (3/4 )
C) 4 (1/2) D) 3
 
Answer & Explanation Answer: C) 4 (1/2)

Explanation:

Work done by P alone in one day = 1/6th of the total work done by Q alone in one day = 1/3(of that done by P in one day) = 1/3(1/6 of the total) = 1/18 of the total.

Work done by P and Q, working together in one day = 1/6 + 1/18  = 4/18 = 2/9 of the total
 
They would take 9/2 days = 4 (1/2) days to complete the work working together.
Report Error

View Answer Workspace Report Error Discuss

1 44
Q:

A can do a piece of work in 30 days. He works at it for 6 days and then B finishes it in 18 days. In what time can A and B together it ?

A) 14 1/2 days B) 11 days
C) 13 1/4 days D) 12 6/7 days
 
Answer & Explanation Answer: D) 12 6/7 days

Explanation:

Let 'B' alone can do the work in 'x' days

6/30 + 18/x = 1
x = 22.5
1/30 + 1/22.5 = 7/90

=> 90/7 = 12 6/7 days

Report Error

View Answer Workspace Report Error Discuss

5 151
Q:

Two persons K and L can complete a piece of work in 30 days and 45 days respectively. If they work together, what part of the work will be completed in 3 days ?

A) 1/6 B) 1/3
C) 2/3 D) 1/18
 
Answer & Explanation Answer: A) 1/6

Explanation:

K's one day's work = 1/30
L's one day's work = 1/45
(K + L)'s one day's work = 1/30 + 1/45 = 1/18

The part of the work completed in 3 days = 3 (1/18) = 1/6.

Report Error

View Answer Workspace Report Error Discuss

2 95