PMP Certification Questions

Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Plan Purchase and Acquisitions?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project management plan


                 - Risk register


                 - Risk - related contractual agreements


                 - Resource requirements


                 - Project schedule


                 - Activity cost estimates


                 - Cost baseline


II. Tools and Techniques



  • Make-or-buy analysis

  • Expert judgement

  • Contract types


III. Outputs



  • Procurement management plan

  • contract statement of work

  • make-or-buy decisions

  • Requested changes       

Report Error

View answer Workspace Report Error Discuss

0 1689
Q:

Project Management Processes

What is the underlying concept for the interaction among the project management processes?

Answer

Plan-do-check-act cycle

Report Error

View answer Workspace Report Error Discuss

0 1685
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Acquire Project Team?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Roles and responsibilities 

  • Project organization charts

  • Staffing management plan


II. Tools and Techniques



  • Pre-assignment

  • Negotiation

  • Acquisition

  • Virtual teams


III. Outputs



  • Project staff assignments

  • Resource availability

  • Staffing management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1685
Q:

Importance of project life cycle?

Answer

A project has a beginning and an end and passes through several phases of development known as life cycle phases. Every project has certain phases of development. A clear understanding of these phases allows managers and executives to maintain control of the project more efficiently.
These phases are varied depending upon the industry involved but all follow the same basic steps.


 


How Important is Project Life Cycle::


1. This is a tried and tested method for delivering projects on time, within budget and to the expected quality targets.


2. Aids communication and helps define roles within the project organisation as it provides a framework for the project that is visible and understood by all members of the project.


3. The project lifecycle will allow the project manager to link progress directly to each phase and recognise the completion of each phase


4. The phases within the project lifecycle provide an understanding of the evolution of the project, being able to identify areas that need greater attention at different times such as risk management in the early stages and more Project Evaluation Reviews during the Implementation stage.


5. At each stage, approval is generally required from outside the project team before proceeding to the next stage.


6. The project life cycle also allows for the gate procedure to be used.


7. At each stage, approval is generally required from outside the project team before proceeding to the next stage.

Report Error

View answer Workspace Report Error Discuss

4 1685
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Resource Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Activity list

  • Activity attributes

  • Resource availability

  • Project management plan


II. Tools and Techniques



  • Expert Judgment

  • Alternatives analysis

  • Published estimating data

  • Project management software

  • Bottom-up estimating


III. Outputs



  • Activity resource requirements

  • Activity atributes (updates)

  • Resource breakdown structure

  • Resource calendars (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 1683
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Develop Project Team?

Answer

I. Inputs



  • Project staff assignments

  • Staffing management plan

  • Resource availability


II. Tools and Techniques



  • General management skills

  • Training

  • Team - building activities

  • Ground rules

  • Co-location

  • Recognition and rewards


III. outputs



  • Team performance assessment

Report Error

View answer Workspace Report Error Discuss

0 1679
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Development?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Project schedule network diagrams

  • Activity resource requirements

  • Resource calendars

  • Activity duration estimates 

  • Project management plan


                - RisK register


II. Tools and Techniques



  • Schedule network analysis

  • Critical path method

  • Schedule compression

  • What-if scenario analysis

  • Resource leveling

  • Critical chain method

  • Project management software

  • Applying calendars

  • Adjusting leads and lags 

  • Schedule model


III. Outputs



  • Project schedule

  • Schedule model data

  • Schedule baseline

  • Resource requirements (updates)

  • Activity attributes (updates)

  • Project calendar (updates)

  • Requested changes

  • Project management plan (updates)


                 - Schedule management plan(updates)

Report Error

View answer Workspace Report Error Discuss

0 1670
Q:

Project Management - Introduction

What is Portfolio Management?

Answer

A Portfolio is a collection of projects or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives.

Report Error

View answer Workspace Report Error Discuss