Q:

Why are CPM, GERT, and PERT not considered sufficient to create a project schedule?

A) All three are tools and techniques of schedule development, not the actual schedule B) As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations
C) They are sufficient. Each calculates early and late start and finish dates for each activity D) They are Monte Carlo techniques used to provide what-if analysis for adverse external factors on a project
 
Answer & Explanation Answer: B) As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations

Explanation:

Answer A is tempting because it is true by definition, but Answer B is correct because it properly answers the question, in that these techniques do not take into account resource pool constraints. Answer C is incorrect because it provides possible early and late start and finish dates, but not the actual schedules. Answer D is incorrect because none of the the three are simulation techniques. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Why are risk tolerances and thresholds important to identify in the risk management Plan?

A) Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution B) Tolerances and thresholds help to define how often the risk management process will be performed
C) Tolerances and thresholds determine what tools and data sources will be used in risk management D) Tolerances and thresholds provide the basis for costing the risk management process as well as defining how risk activities will be recorded
 
Answer & Explanation Answer: A) Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution

Explanation:

Answer B defines the timing that should be addressed in the risk management plan. Answer C defines the methodology that should be identified in a risk management plan. Answer D touches on the budgeting and tracking that should be defined in the risk management plan.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

On a systems development project, Richard needs two programmers. He knows John and Smith were able to create a program in 40 days similar to the one he wants to create on his project. He decides to use 40 days as his estimate. This is an example of what type of estimating?

A) Parametric modeling B) Analogous
C) Rule of thumb D) Fixed Rate
 
Answer & Explanation Answer: B) Analogous

Explanation:

Richard is using an estimate based on a project very similar to to his own with staff he will be using.  Answer A is incorrect because perametric modeling involves using a mathematical model to predict costs, such as dollars per line of code. Answer C is incorrect, although close; if the development project is a common item, such as putting down new flooring, a rule -of-thumb measurement can be used, although it is less accurate. Answer D is incorrect because it is not a form of estimating, but a type of pricing.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction  phase of a project. you are currently in the process of activity sequencing. This is a example of what?

A) Gatekeeping B) Milestone
C) New scope for the project D) Project integration
 
Answer & Explanation Answer: B) Milestone

Explanation:

The approval by the Architecture Review Board is a milestone you want to include in activity sequencing so that you can ensure the requirements for meeting the review board's approval are met.  Answer A is tempting because the question references phase-end activities; however, it is not an example of gatekeeping because the project is not being authorized to continue based only on the architecture review.Gatekeeping often involves the review of other factors as well. Answer C is incorect because the requirement of a review board approval does not afect scope. Answer D is incorrect because project integration planning involves project plan development, execution, and integrated change control, which are not related to a review board.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

You are working on a new project to develop a new wireless product with ease - of - use features recommended by customers. It is as yet undetermined which features and the extent to which each feature will be incorporated into the product.You have a focus group that will continue to evaluate the features as the project goes forward.The focus group is authorized to suggest changes, as are your engineers and the quality department.As a project manager, what will help you most to minimize the effect of these changes?

A) A change management plan B) A scope management plan
C) Do not continue with the project until all of the features are clearly defined in the scope statement and scope definition. D) This is an expected part of every project. A good project manager will have a communications plan in place to be sure everyone knows what is happening on the project.
 
Answer & Explanation Answer: B) A scope management plan

Explanation:

Answer A is tempting because the problem focuses on changes. However, because we are talking about the elaboration of the product's characteristics, we are talking about scope changes, and therefore Answer B is the best answer. Answer C is also tempting because it is difficult to more forward on a project until the scope is clearly defined (especially in systems development projects), but with products and certain types of web development, scope changes can be frequent, and a formal scope management plan is needed. Answer D is true from a project perspective, but does not addres the scope issues.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

A Good CFO will tell you that it is important to look at your bottom line and determine how to increase profits for the organization. Veronica, the new CFO at a local university, is taking that approach and applying it to new projects. Therefore,she wants to include costs from each phase of the project on a total expenditure is known as 

A) An opportunity cost B) A sunk cost
C) NPV D) A life cycle
 
Answer & Explanation Answer: D) A life cycle

Explanation:

Life Cycle costing includes the costs from each phase of the project life cycle when the total investment costs are calculated. Answer A is incorrect because an opportunity cost is the difference between a chosen investment and the one that is passed up. Answer B is incorrect because sunk costs are costs that have been incurred and cannot be reversed. Answer C is incorrect because net present value (NPV) is the present value of cash inflows(benifits) minus the present value of cash outflows (costs).

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

You are a project manager for the redevelopment of the Hoover Dam. Your team has been provided with the scope statement, but it lacks many description details. Your team is concerned because the project is in the initiation phase and it wants to postpone it until it has more information. As the project manager, you recommend that

A) The team should go forward, but be caution about the lack of details and the impact upon the timeline for the project B) The project should not go forward until the stakeholders agree about the scope and purpose of the project
C) The team should verify the scope and realize that more details will be available as more project characteristics are progressively elaborated. D) The team should review the project selection criteria for the Hoover Dam project
 
Answer & Explanation Answer: C) The team should verify the scope and realize that more details will be available as more project characteristics are progressively elaborated.

Explanation:

The project details and description will usually have less detail at the beginning of the project and will increase as the characteristics are progressively elaborated. Answer A is incorrect because the team should confirm that they understand the esence of the scope of the project, even if the details might be ambiguous at the beginning of the project. Answer B is incorrect because the project should go forward; however, the team should request further clarification of what the project scope entails. Answer D is incorrect because the project selection criteria should be established before the project begins.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Subject matters experts (SMEs) are resources that are imperative to the succes of a project. Many times, project managers are not experts in the areas they are managing and frequently must rely upon other's expertise. In which scope - management process are SMEs first used?

A) Scope planning B) Scope definition
C) Initiation D) Scope verification
 
Answer & Explanation Answer: C) Initiation

Explanation:

Initiation is the first step in the scope management process, and expert judgment is one of the techniques routinely utilized. Answers A, B, and D are incorrect because they would come after the initiation process.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification