Q:

By monitoring ad campaign performance, an advertiser may obtain the information needed to

A) determine if campaigns are meeting overall marketing and conversion goals B) create additional AdWords accounts for low-performing keywords
C) compare campaign performance to that of individual competitors D) create duplicate ad groups with identical keywords and different ad variations
 
Answer & Explanation Answer: A) determine if campaigns are meeting overall marketing and conversion goals

Explanation:

By monitoring ad campaign performance an advertiser may obtain the information needed to determine if campaigns are meeting overall marketing and conversion goals compare campaign performance to that of other advertisers create separate adwords accounts for low-performing keywords create duplicate ad groups with identical keywords and different ad variations.

Report Error

View Answer Report Error Discuss

Filed Under: Advertising and Media

0 2097
Q:

What are turnaround time and response time?

Answer

Turnaround time is the interval between the submission of a job and its completion. Response time is the interval between submission of a request, and the first response to that request.

Report Error

View answer Workspace Report Error Discuss

1 2097
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Development?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Project schedule network diagrams

  • Activity resource requirements

  • Resource calendars

  • Activity duration estimates 

  • Project management plan


                - RisK register


II. Tools and Techniques



  • Schedule network analysis

  • Critical path method

  • Schedule compression

  • What-if scenario analysis

  • Resource leveling

  • Critical chain method

  • Project management software

  • Applying calendars

  • Adjusting leads and lags 

  • Schedule model


III. Outputs



  • Project schedule

  • Schedule model data

  • Schedule baseline

  • Resource requirements (updates)

  • Activity attributes (updates)

  • Project calendar (updates)

  • Requested changes

  • Project management plan (updates)


                 - Schedule management plan(updates)

Report Error

View answer Workspace Report Error Discuss

0 2097
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Control ?

Answer

I. Inputs



  • Schedule management plan

  • Schedule baseline

  • Performance reports

  • Approved change requests


II. Tools and Techniques



  • Progress reporting

  • Schedule change control system

  • Performance measurement

  • Project management software

  • Variance analysis

  • Schedule comparision bar charts


III. Outputs



  • Schedule model data (updates)

  • Schedule baseline (updates)

  • Performance measurements

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Activity list (updates)

  • Activity attributes (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2097
Q:

Which is the national game of pakistan ?

A) Cricket B) Kabaddi
C) Archery D) Hockey
 
Answer & Explanation Answer: D) Hockey

Explanation:

hockey

Report Error

View Answer Report Error Discuss

Filed Under: Sports
Exam Prep: Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2096
Q:

What is the unit of the physical quantity "Stress"?

A) newton second B) steradian
C) pascal D) joule
 
Answer & Explanation Answer: C) pascal

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: Bank Exams , CAT

1 2096
Q:

Who owns Tradestation?

A) SBI Group B) Monex Group, Inc.
C) CME Group D) None of the above
 
Answer & Explanation Answer: B) Monex Group, Inc.

Explanation:

Tradestation is owned by its parent organization Monex Group, Inc.

Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2096
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Quantitative Risk Analysis?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Risk management plan

  • Risk register

  • Project management plan


                 - Project schedule management plan


                 - Project cost management plan


II. Tools and Techniques



  • Data gathering and representation techniques

  • Quantitative risk analysis and modeling techniques


III. Outputs



  • Risk register (updates)