Q:
      
      
         
            
P can complete a work in 12 days working 8 hours a day.Q can complete the same work in 8 days working 10 hours a day. If both p and Q work together,working 8 hours a day,in how many days can they complete the work?
         
       
      
      
      
          
      
      
          Answer & Explanation
         Answer: A) 60/11         
         
Explanation: P can complete the work in (12 x 8) hrs = 96 hrs 
Q can complete the work in (8 x 10) hrs=80 hrs 
Therefore, P's 1 hour work=1/96   and Q's 1 hour work= 1/80
(P+Q)'s 1 hour's work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs  
Therefore, Number of days of 8 hours each = (480/11) x (1/8) = 60/11
       
      
      
      
          View Answer
          Report Error
          Discuss