12 men can complete a work in 8 days. 16 women can complete the same work in 12 days. 8 men and 8 women started working  and worked for 6 days. How many more men are to be added to complete the remaining work in 1 day?
         
       
      
      
      
          
      
      
          Answer & Explanation
         Answer: B) 12         
         
Explanation: 1 man's 1 day work =1/96 ; 1 woman's 1 day work = 1/192
Work done in 6 days= 
Remaining work = 1/4
(8 men +8 women)'s 1 day work =  =1/8
Remaining work =1/4 -  1/8 = 1/8
 
 1/96 work is done in 1 day by 1 man
 
Therefore, 1/8 work will be done in 1 day by 96 x (1/8) =12 men
       
      
      
      