Q:

X and Y together can do a piece of work in 30 days. Y and Z together can do the work in 20 days. X starts the work and works for 15 days then Y takes that work and works for 27 days. Finally Z finishes the remaining work in 9 days. In how many days Y alone can complete the entire work?

 

A) 60 B) 45
C) 50 D) 65
 
Answer & Explanation Answer: A) 60

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 2014
Q:

A and B can together do a piece of work in 10 days. If A works with twice of his efficiency and B works with an efficiency 1/3rd less than his efficiency, then the work gets completed in 6 days. In how many days can A and B do the work alone respectively?

A) 40/3, 40 B) 20/3, 20
C) 30, 20/3 D) 50/3, 25
 
Answer & Explanation Answer: A) 40/3, 40

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2010
Q:

Find the circumference (in cm) of a circle of radius 7 cm.

 

A) 56 B) 44
C) 16 D) 32
 
Answer & Explanation Answer: B) 44

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams

2 2008
Q:

Two cars start from a house at an interval of 10 min and travel at a speed of 20 kmph. With how much speed should a woman coming from the opposite direction towards the house travel, to meet the cars at an interval of 8 min?

A) 5 B) 6
C) 7 D) 4
 
Answer & Explanation Answer: A) 5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Distance
Exam Prep: Bank Exams

9 2004
Q:

A takes 24 day in completing a work alone. Time taken by A in completing 1/3rd of the work is equal to the time taken by B in completing half of the work. How many days will be taken in completing the work if both A & B start working together?

A) 21/3 days B) 48 days
C) 40 days D) 48/5 days
 
Answer & Explanation Answer: D) 48/5 days

Explanation:

Ans. 
Time taken by A to complete a work alone - 24 days
Time taken by A in completing 1/3 of work = 24*1/3= 8 Days
8 day = time taken by B in completing 1/2 of work
B alone can complete the work = 16 days
The required time in completing the work if both A & B start working together?
16*24 / 40 = 48/5 Days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , GATE

2 2000
Q:

48 people could complete a task in 17 days. After 6 days, 4 of the workers left. How many days from then will it take to complete the task?

A) 12 B) 13
C) 15 D) 16
 
Answer & Explanation Answer: A) 12

Explanation:

Given, 48 people can do a work in 17 days. So total work = 48 x 17 = 816
Work done by 48 people in 6 days = 288.

The remaining work = 816 - 288 = 528
After 6 days four workers left. So number of people working is 44
Total number of days required for 44 men to complete the remaining work = 528/44 = 12

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT

1 1998
Q:

5% of 400000?

A) 4000 B) 16000
C) 8000 D) 20000
 
Answer & Explanation Answer: D) 20000

Explanation:

5% of 400000

= 5 x 400000/100

= 20,000

 

Hence, 5% of 4,00,000 = 20,000

Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

17 1997
Q:

The ratio of speed of three racers is 3 : 4 : 6. What is the ratio of time taken by the three racers to cover the same distance?

 

A) 3:4:6 B) 6:4:3
C) 4:3:2 D) 2:3:5
 
Answer & Explanation Answer: C) 4:3:2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Ratios and Proportions
Exam Prep: Bank Exams

3 1996