Quantitative Aptitude - Arithmetic Ability Questions

Q:

Prahlad has done 1/3rd of a job in 30 days, Sarfaraz completes the rest of the job in 90 days. In how many days can they together do the job?

A) 27 days B) 18 days
C) 54 days D) 36 days
 
Answer & Explanation Answer: C) 54 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1759
Q:

X and Y started a business investing Rs 12000 and Rs 9000 respectively. After 4 months, X left the business and Z joined the business by investing Rs. 18000. At the end of the year, there was a profit of Rs 12500. What is the share (in Rs) of Z in the profit?

 

A) 6000 B) 4500
C) 7200 D) 7500
 
Answer & Explanation Answer: A) 6000

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Partnership
Exam Prep: Bank Exams

3 1759
Q:

A wholesaler sells a watch to a retailer at a gain of 35% and the retailer sells it to a customer at a loss of 25%. If the customer pays Rs 2379.375, what had it cost the wholesaler?

A) Rs 2350 B) Rs 2409
C) Rs 2928 D) Rs 2291
 
Answer & Explanation Answer: A) Rs 2350

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Profit and Loss
Exam Prep: Bank Exams

2 1759
Q:

A grocer had 1600 kgs of wheat. He sold a part of it at 20% profit and the rest at 12% profit, so that he made a total profit of 17%. How much wheat (in kg) did he sell at 20% profit?

A) 600 B) 1000
C) 800 D) 1200
 
Answer & Explanation Answer: B) 1000

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Profit and Loss
Exam Prep: Bank Exams

3 1758
Q:

20 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?

 

A) 8 B) 10
C) 15 D) 20
 
Answer & Explanation Answer: B) 10

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 1758
Q:

P can make a table in 16 days while Q can make it in 20 days. Q started the work and did that work for 5 days. In how many days P can complete the remaining work?

 

A)  10 B)  12
C)  15 D) 18
 
Answer & Explanation Answer: B)  12

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1758
Q:

In the following question, select the odd letters from the given alternatives.

A) ACFJ B) RTWA
C) NPSV D) HJMQ
 
Answer & Explanation Answer: C) NPSV

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

0 1758
Q:

Makarand works 2 times as fast as Samarjit. If Samarjit can complete a job alone in 27 days, then in how many days can they together finish the job?

A) 6 days B) 7 days
C) 5 days D) 9 days
 
Answer & Explanation Answer: D) 9 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1757