Project Scope Management

What are the Project Management Processes included in the Project Scope Management?

Answer

Scope Planning - Creating a project scope management plan that documents how the project scope will be defined,verified, controlled, and how the work breakdown structure (WBS) will be created and defined.


Scope Definition - Developing a detailed project scope statement as the basis for future project decisions.


Create WBS - Subdividing the major project deliverables and project work into smaller, more manageable components


Scope Verification - Formalizing acceptance of the completed project deliverables.


Scope Control - Controlling changes to the project scope.

Report Error

View answer Workspace Report Error Discuss

0 2148
Q:

Improve the bracketed part of the sentence.
The stranded pilgrims (had waited) in the bitter cold for more than two hours now.

A) has been waiting B) have been waiting
C) have waited D) no improvement
 
Answer & Explanation Answer: B) have been waiting

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2148
Q:

Improve the bracketed part of the sentence.
All the allegations levelled (over) the poor watchman were found to be baseless.

A) upon B) off
C) against D) no improvement
 
Answer & Explanation Answer: C) against

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2148
Q:

Select the word with the correct spelling.

A) blamefull B) procsimal
C) hilocky D) miracles
 
Answer & Explanation Answer: D) miracles

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2148
Q:

Which city is the venue of the World Government Summit 2019?

A) Dubai B) Hyderabad
C) New York D) Singapore
 
Answer & Explanation Answer: A) Dubai

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2148
Q:

The Waste to Wonder park is in?

A) Pune B) Gujarat
C) Delhi D) Hyderabad
 
Answer & Explanation Answer: C) Delhi

Explanation:

The "Waste to Wonder” park is in south Delhi.

Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

3 2148
Q:

The taper on the lathe spindle is

A) 1 in 10 B) 1 in 20
C) 1 in 15 D) 1 in 25
 
Answer & Explanation Answer: B) 1 in 20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk

4 2148
Q:

Most stars are at what point in their life cycles?

A) Supernova B) Protostar
C) Red Giant D) Main Sequence
 
Answer & Explanation Answer: D) Main Sequence

Explanation:

most_stars_are_at_what_point_in_their_life_cycles1560330646.jpg image

Most stars are at main sequence point in their life cycles.

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2147