Questions

Q:

French Revolution was started in the Year ?

A) 1786 B) 1787
C) 1788 D) 1789
 
Answer & Explanation Answer: D) 1789

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World History

1 2350
Q:

Which amongst the following is not a component of monetary policy in India?

A) Repo rate B) Moral suasion
C) Credit Rationing D) Public Debt
 
Answer & Explanation Answer: D) Public Debt

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Economy
Exam Prep: Bank Exams

1 2349
Q:

What has feet and legs and nothing else?

Answer

Stocking is long sock that women wore which has legs and feet and nothing else.

Report Error

View answer Workspace Report Error Discuss

Subject: Word Puzzles Exam Prep: GRE , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

1 2348
Q:

Clossing Process Group

What are the Project Management Processes included in Closing Process Group?

Answer


    • Close Project

    • Contract Closure



 

Report Error

View answer Workspace Report Error Discuss

0 2348
Q:

For an object, the state of rest is considered to be the state of ______ speed.

A) increasing B)
C) inverse D) zero
 
Answer & Explanation Answer: D) zero

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: Bank Exams

4 2348
Q:

'Agronomy' is the practice of raising ______________

A) Plants and Animals B) Crop plants
C) Agriculture D) Fruit plants only
 
Answer & Explanation Answer: A) Plants and Animals

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: Bank Exams

1 2347
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Close project Phase?

Answer

I. Inputs



  • Project management plan

  • Contract documentation

  • Enterprise environmental factors

  • Organizational process assets

  • Work performance information

  • Deliverables


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Administrative closure procedure

  • Contract closure procedure

  • Final product, service, or result

  • Organisational process assets (updates)

Report Error

View answer Workspace Report Error Discuss

0 2347
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Duration Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Activity resource requirements

  • Resource calendars

  • Project management plan


               - Risk register


               - Activity cost estimates


II. Tools and Techniques



  • Expert judgment

  • Analogous  estimating

  • Parametric estimating

  • Three-point estimates 

  • Reserve analysis


III. Outputs



  • Activity duration estimates

  • Activity attributes (updates)

Report Error

View answer Workspace Report Error Discuss