Q:
      
      
         
            
A, B and C can complete a work in 20, 24 and 30 days respectively. All three of them starts together but after 4 days A leaves the job and B left the job 6days before the work was completed. C completed the remaining work alone. In how many days was the total work completed?
         
       
      
      
      
          
      
      
      
      
      