Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Development?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Project schedule network diagrams

  • Activity resource requirements

  • Resource calendars

  • Activity duration estimates 

  • Project management plan


                - RisK register


II. Tools and Techniques



  • Schedule network analysis

  • Critical path method

  • Schedule compression

  • What-if scenario analysis

  • Resource leveling

  • Critical chain method

  • Project management software

  • Applying calendars

  • Adjusting leads and lags 

  • Schedule model


III. Outputs



  • Project schedule

  • Schedule model data

  • Schedule baseline

  • Resource requirements (updates)

  • Activity attributes (updates)

  • Project calendar (updates)

  • Requested changes

  • Project management plan (updates)


                 - Schedule management plan(updates)

Report Error

View answer Workspace Report Error Discuss

0 2127
Q:

Improve the bracketed part of the sentence.
The workers are bent (on) getting a full months pay as bonus.

A) for B) upon
C) to D) no improvement
 
Answer & Explanation Answer: B) upon

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2127
Q:

A sentence/a part of the sentence is underlined. Four alternatives are given to the underlined part which will improve the sentence. Choose the correct alternative and click the button corresponding to it. In case no improvement is needed, click the button corresponding to "No improvement".

He is suffering from fever for a week.

A) was suffering B) had suffering
C) has been suffering D) No improvement
 
Answer & Explanation Answer: C) has been suffering

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2126
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope control ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project scope management plan

  • Performance reports

  • Approved change requests

  • Work performance information


II. Tools and Techniques



  • Change control system

  • Variance analysis

  • Replanning

  • Configuration management system


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure(updates)

  • WBS dictionary (updates)

  • Scope baseline (updates)

  • Requested changes

  • Recommended  corrective action

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2126
Q:

Other things equal an improvement in productivity will

A) shift the aggregate demand curve to the left B) shift the aggregate supply curve to the right
C) increase the equilibrium price level D) shift the aggregate supply curve to the left
 
Answer & Explanation Answer: B) shift the aggregate supply curve to the right

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Business Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

4 2126
Q:

What's the speed and device maximum specs for Firewire?

Answer

IEEE 1394 (Firewire) supports the maximum of 63 connected devices with speeds upto 400 Mbps.

Report Error

View answer Workspace Report Error Discuss

Subject: Hardware

0 2126
Q:

Hydro-electric power provides more than 90% of the total power consumed in 

A) Norway B) Sweden
C) India D) UK
 
Answer & Explanation Answer: A) Norway

Explanation:

The short and swift streams running down the Scandinavian mountains have been harnessed for power which also compensates for the absence of coal and oil.

Report Error

View Answer Report Error Discuss

Filed Under: World Geography

1 2125
Q:

Read the passage carefully and choose the best answer to each question out of the four alternatives and click the button corresponding to it.

Reporters and city officials gathered at a Chicago railroad station one afternoon in 1953. The person they were meeting was the 1952 Nobel Peace Prize winner. A few minutes after the train came to a stop, a giant of a man - six feet four inches - with bushy hair and a large moustache stepped out from the train. Cameras flashed. City officials approached him with hands outstretched. Various people began telling him how honoured they were to meet him.

The man politely thanked them and then, looking over their heads, asked if he could be excused for a moment. He quickly walked through the crowd until he reached the side of an elderly black woman who was struggling with two large suitcases. He picked up the bags with a smile, escorted the woman to a bus. After helping her aboard, he wished her a safe journey. As he returned to the greeting party he apologized, "Sorry to have kept you waiting." Not many whites would have done what he did.

The man was Dr. Albert Schweitzer, the famous missionary doctor who had spent his life helping the poor in Africa. In response to Dr. Schweitzer's action, one member of the reception committee said with great admiration to the reporter standing next to him, "That's the first time I ever saw a sermon walking."


Dr. Albert delighted _____ .

A) in being helped by others B) in not being honoured
C) in being honoured D) in helping others
 
Answer & Explanation Answer: D) in helping others

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2125