Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Monitor and Control Project Work phase?

Answer

I. Inputs



  • Project management plan

  • Work performance information

  • Rejected Change requests


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Earned value technique

  • Expert Judgment


III. Outputs



  • Recommended corrective actions

  • Recommended preventive actions

  • Forecasts

  • Recommended defect repair

  • Requested changes 

Report Error

View answer Workspace Report Error Discuss

1 2015
Q:

What is the capital of Denmark?

A) Copenhagen B) Stockholm
C) Vienna D) Oslo
 
Answer & Explanation Answer: A) Copenhagen

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Country Capitals
Exam Prep: Bank Exams

2 2014
Q:

What are the benefits of multithreaded programming?

Answer

 



  • Responsiveness

  • Resources sharing

  • Economy

  • Utilization of multiprocessor architectures.

Report Error

View answer Workspace Report Error Discuss

1 2014
Q:

Which state police has launched e-learning portal 'Nipun' for training its personnel?

A) Delhi B) Uttar Pradesh
C) Telangana D) Maharashtra
 
Answer & Explanation Answer: A) Delhi

Explanation:

Delhi state police has launched e-learning portal 'Nipun' for training all its police officers to give up to date information through specialized courses designed by experts.

Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 2014
Q:

The official currency of United Kingdom -

A) Pound Sterling B) Renminbi
C) Euro D) Dollar
 
Answer & Explanation Answer: A) Pound Sterling

Explanation:

Pound Sterling is the official currency of United Kingdom.

 

-> Renminbi is the currency of China.

-> Euro is the currency of 19 countries like Spain, Austria, Finland, Italy, Germany, Greece, Belgium, etc...

-> Dollar is the currency of United States.

Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

4 2013
Q:

If i wanted to reach the South Atlantic from the South Pacific while touching South America , I would have to use

A) Florida Straits B) Dardaelles
C) Magellan Straits D) Bosporus
 
Answer & Explanation Answer: C) Magellan Straits

Explanation:

a) joins the Gulf of Mexico and Atlantic Ocean, and touches USA and Bahama Island.

b) joins the sea of Marmara and Aegean Sea, touching Asian Turckey and European  Turkey

d) joins Black sea and sea of Marmara touching Asian Turkey and European Turkey

Report Error

View Answer Report Error Discuss

Filed Under: World Geography

0 2013
Q:

Project Time Management

What are the Project Management Processes included in the Project Time Management?

Answer

Activity Definition - Identifying the Specific schedule activities that need to be performed to produce the various project deliverables.


Activity Sequencing - Identifying and documenting dependencies among schedule activities


Activity Resource Estimating - Estimating the type and quantities of resources required to perform each schedule activity


Activity Duration Estimating - Estimating the number of work periods that will be needed to complete individual schedule activities


Schedule Development - Analyzing activity sequences, durations, resource requirements, and schedule constraints to creae the project schedule.


Schedule Control - Controlling changes to the project schedule

Report Error

View answer Workspace Report Error Discuss

0 2012
Q:

Increased wind speed is accompanied by a reduced air _____________.

A) humidity B) pressure
C) density D) aridity
 
Answer & Explanation Answer: B) pressure

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics

2 2012