Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?

A) 6 B) 12
C) 9 D) 15
 
Answer & Explanation Answer: A) 6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2193
Q:

If A, B and C together do a job in 4 days, A and C together do the job in 4.5 days and B and C together do the job in 12 days then in how many days can C alone do the job?

A) 36 B) 6
C) 18 D) 12
 
Answer & Explanation Answer: C) 18

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2189
Q:

A, B and C together can complete a work in 25 days. If the ratio of efficiency of A, B and C is 15 : 10 : 6 respectively, then in how many days C alone can complete the same work?

A) 727/6 B) 725/6
C) 775/6 D) 745/6
 
Answer & Explanation Answer: C) 775/6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams , CAT

0 2185
Q:

A, B and C can do a job working alone in 12, 16 and 24 days respectively. In how many days they can do the job if they worked together?

A) 16/3 B) 15/4
C) 17/3 D) 19/4
 
Answer & Explanation Answer: A) 16/3

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2177
Q:

P and Q can do a project in 150 and 100 days respectively. In how many days can they complete 60% of the project if they work together?

A) 12 days B) 72 days
C) 42 days D) 36 days
 
Answer & Explanation Answer: D) 36 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2172
Q:

A can do a work in 36 days and B in 12 days. If they work on it together, then in how many days will they be able to do the work?

A) 8 B) 6
C) 10 D) 9
 
Answer & Explanation Answer: D) 9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2163
Q:

A and B have to type a book together containing 120 pages. A takes 9 hrs to type 36 pages and B takes 5 hrs to type 40 pages. A typed first 60 pages alone and the last 60 pages were typed by A and B together. How much time (in hours) will be taken to type the complete book?

A) 24 B) 20
C) 12 D) 15
 
Answer & Explanation Answer: B) 20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

7 2161
Q:

X can complete 5/7 part of a work in 10 days and Y can complete 3/4 part of the same work in 9 days. In how many days will both complete 13/21 part  of the total work?

 

A)  6 B) 4
C) 3 D) 12
 
Answer & Explanation Answer: B) 4

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

8 2151