Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Sumit is 28% less efficient than Amit. If Amit can make a wall in 54 days, then Sumit can complete the same work in how many days?

 

A) 75 B) 70
C) 72 D) 76
 
Answer & Explanation Answer: A) 75

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1816
Q:

A can do as much work in 4 days as B can do in 5, and B can do as much work in 6 days as C in 7. In what time will C do a piece of work which A can do in a week ?

A) 10 5/24 days B) 4 4/5 days
C) 6 8/15 days D) 12 6/19 days
 
Answer & Explanation Answer: A) 10 5/24 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1814
Q:

Anil is twice as good as workman as Bimal and together they finish a piece of work in 9 days. In how many days will Anil alone finish the work?

A) 12.5 B) 11.5
C) 10.5 D) 13.5
 
Answer & Explanation Answer: D) 13.5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1807
Q:

A can do a work in 36 days and B in 12 days. If they work on it together for 3 days, then what fraction of work is left?

A) 2/3 B) 1/3
C) 1/4 D) 1/5
 
Answer & Explanation Answer: A) 2/3

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1806
Q:

X, Y and Z can do a piece of work in 30,40 and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?

A) 660/47 B) 640/47
C) 680/47 D) 665/47
 
Answer & Explanation Answer: A) 660/47

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams , CAT

1 1797
Q:

A can do a work in 20 days and B in 50 days. If they work on it together for 5 days, then what fraction of work is left?

A) 13/20 B) 1/3
C) 1/6 D) 2/9
 
Answer & Explanation Answer: A) 13/20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1796
Q:

If 10 people can do a job in 20 days,then 20 people with twice the efficiency can do the same job in

A) 5 days B) 10 days
C) 20 days D) 40 days
 
Answer & Explanation Answer: A) 5 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1792
Q:

Mahanath works 2 times as fast as Sahay. If Sahay can complete a job alone in 21 days, then in how many days can they together finish the job?

A) 7 days B) 6 days
C) 5 days D) 2 days
 
Answer & Explanation Answer: A) 7 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1791