Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is

A) 20 B) 35
C) 30 D) 25
 
Answer & Explanation Answer: D) 25

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1557
Q:

If 10 people can do a job in 20 days,then 20 people with twice the efficiency can do the same job in

A) 5 days B) 10 days
C) 20 days D) 40 days
 
Answer & Explanation Answer: A) 5 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1556
Q:

Makarand works 2 times as fast as Samarjit. If Samarjit can complete a job alone in 27 days, then in how many days can they together finish the job?

A) 6 days B) 7 days
C) 5 days D) 9 days
 
Answer & Explanation Answer: D) 9 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1550
Q:

20 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?

 

A) 8 B) 10
C) 15 D) 20
 
Answer & Explanation Answer: B) 10

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 1546
Q:

Anil is twice as good as workman as Bimal and together they finish a piece of work in 9 days. In how many days will Anil alone finish the work?

A) 12.5 B) 11.5
C) 10.5 D) 13.5
 
Answer & Explanation Answer: D) 13.5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1540
Q:

Parimal has done 1/4th of a job in 10 days, Salim completes the rest of the job in 20 days. In how many days can they together do the job?

A) 8 days B) 24 days
C) 12 days D) 16 days
 
Answer & Explanation Answer: D) 16 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 1536
Q:

A  field  can  be  reaped  by  12  men  or  18  women  in  14  days.  In  how  many  days  can  8  men  and  16 women reap it?

A) 26 days B) 24 days
C) 9 days D) 8 days
 
Answer & Explanation Answer: C) 9 days

Explanation:
12 men or 18 women can complete in 14 days
8 men and 16 women can complete in how many days
12men = 18 women (Comparing efficiencies)
1men = 18/12 = 1.5 women
8 men and 16 women = 12women + 16 women = 28 women
18 women completes in 14 days
1 woman completes in 14*18 days
28 women completes in (14*18)/28 days = 9 days
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1524
Q:

24 men can repair a road in 50 days. If they are joined by 16 more men, then in how much time (in days) the road can be repaired?

A) 28 B)  25
C) 32 D) 30
 
Answer & Explanation Answer: D) 30

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1518