Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

12 men or 30 boys can complete a work in 72 days. How many days will 48 men and 24 boys will take to complete the same work?

A) 20 B) 18
C) 15 D) 25
 
Answer & Explanation Answer: C) 15

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1212
Q:

A and B can do a piece of work in 72 days. B and C can do it in 120 days and A and C can do it in 90 days. A alone can do it in:

A) 120 days B) 130 days
C) 150 days D) 100 days
 
Answer & Explanation Answer: A) 120 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1209
Q:

Some masons promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of masons?

 

A) 10 B) 21
C) 15 D) 18
 
Answer & Explanation Answer: D) 18

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1199
Q:

Rahul can complete a work in 18 days and Sonu can complete the same work in 15 days. If both together work for 5 days, then what part of total work is left?

 

A) 7/15 B) 11/18
C) 7/18 D) 8/15
 
Answer & Explanation Answer: C) 7/18

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1176
Q:

30 men working 5 hours a day can do a task in 16 days. In how many days will 40 men working 6 hours a day do the same task?

A) 12 days B) 10 days
C) 15 days D) 18 days
 
Answer & Explanation Answer: B) 10 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1174
Q:

In a factory, 60 workers can stitch 120 m of clothes in 7 days, what length of clothes can be stitched by 70 workers in 5 days?

 

A) 100 m B) 90 m
C) 85 m D) 110 m
 
Answer & Explanation Answer: A) 100 m

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1161
Q:

A and B undertake a piece of work for Rs. 250 . A alone can do that work in 5 days and B alone can do that work in 15 days . With the help of C, they finish the work in 3 days . If every one gets paid in proportion to work done by them, the amount C will get is 

A) Rs.50 B) Rs.100
C) Rs.150 D) Rs.200
 
Answer & Explanation Answer: A) Rs.50

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1160
Q:

U, V and W together can make a chair in 20 minutes. U and V together can make it in 25 minutes. How much time will (in minutes) W alone take to make the chair?

 

A) 100   B) 90
C) 60 D) 120
 
Answer & Explanation Answer: A) 100  

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1154