Q:

The distance between places U and V is 1008 km. An express train leaves place U at 9:00 a.m. and runs at a speed of 126 km/hr. The train stops on the way for 20 minutes. At what time (in p.m.) the train will reach at the place V?

A) 6 : 50 B) 3:50
C) 4:20 D) 5:20
 
Answer & Explanation Answer: D) 5:20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Problems on Trains
Exam Prep: GATE , Bank Exams
Job Role: Bank PO , Bank Clerk

2 1575
Q:

Select the odd letters from the given alternatives.

A) RQS B) XWV
C) MLN D) FEG
 
Answer & Explanation Answer: B) XWV

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Analogy
Exam Prep: Bank Exams

0 1574
Q:

Pearl Towers is taller than Sky Towers but shorter than Unity Towers. Unity Towers and Cyber Towers are of same height. Pearl Towers is shorter than Indus Towers. Amongst the buildings, who is the second shortest?

A) Pearl Tower B) Sky Tower
C) Indus Tower D) Unity Tower
 
Answer & Explanation Answer: A) Pearl Tower

Explanation:
Report Error

View Answer Report Error Discuss

4 1574
Q:

In the following question, select the related number from the given alternatives.
5 : 130 : : 6 : ?

A) 210 B) 212
C) 222 D) 242
 
Answer & Explanation Answer: C) 222

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Analogy
Exam Prep: Bank Exams

0 1574
Q:

A trader bought 10 kg of tea at Rs. 400 per kg. He sold half the quantity at 20% loss and remaining at 10% profit. What was his net profit or loss in percentage?

A) 5% loss B) 5% gain
C) 10% loss D) 10% gain
 
Answer & Explanation Answer: A) 5% loss

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Profit and Loss
Exam Prep: Bank Exams

3 1573
Q:

X and Y undertook to do a piece of work for Rs 5400. X alone could do this work in 18 days and Y alone could do this work in 24 days. With the assistance of Z they finished the work in 8 days. What is the share (in Rs) of Z?

 

A) 1200 B) 1500
C) 1600 D) 1800
 
Answer & Explanation Answer: A) 1200

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1573
Q:

What is the unit digit of 15+25+35+...+205 ?

A) 0 B) 5
C) 2 D) 4
 
Answer & Explanation Answer: A) 0

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 1573
Q:

If 9@3=12; 15@4=22; 16@14=4; then what is the value of 6@2=?

A) 26 B) 1
C) 30 D) 8
 
Answer & Explanation Answer: D) 8

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Coding and Decoding
Exam Prep: Bank Exams

0 1573