Aptitude and Reasoning Questions

Q:

Find out which of the answer figures (a), (b), (c) and (d) completes the figure matrix ?

A) a B) b
C) c D) d
 
Answer & Explanation Answer: A) a

Explanation:

The number of components in each row either increases or decreases from left to right . In the third row, it increases.

Report Error

View Answer Report Error Discuss

Filed Under: Figure Matrix

17 3510
Q:

Which of the following relation is CORRECT?

 

I. (√15 + √7) < (2√22)

II. (√17 + √5) < (√20 + √2)

 

A) Only I B) Only II
C) Neither I nor II D) Both I and II
 
Answer & Explanation Answer: A) Only I

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Square Roots and Cube Roots
Exam Prep: Bank Exams

0 3506
Q:

16 persons are participated in a party. In how many differentways can they host the seat in a circular table, if the 2particular persons are to be seated on either side of the host?

A) 16! × 2 B) 14! × 2
C) 18! × 2 D) 14!
 
Answer & Explanation Answer: B) 14! × 2

Explanation:

(16 – 2)! × 2 = 14! × 2

Report Error

View Answer Report Error Discuss

Filed Under: Permutations and Combinations
Exam Prep: Bank Exams

4 3505
Q:

Aarush's birthday is on Thursday 27th April. On what day of the week will be Mitul's Birthday in the same year if Mitul was born on 28th September?

A) Monday B) Thursday
C) Wednesday D) Tuesday
 
Answer & Explanation Answer: B) Thursday

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Calendar
Exam Prep: Bank Exams

15 3503
Q:

A takes 24 day in completing a work alone. Time taken by A in completing 1/3rd of the work is equal to the time taken by B in completing half of the work. How many days will be taken in completing the work if both A & B start working together?

A) 21/3 days B) 48 days
C) 40 days D) 48/5 days
 
Answer & Explanation Answer: D) 48/5 days

Explanation:

Ans. 
Time taken by A to complete a work alone - 24 days
Time taken by A in completing 1/3 of work = 24*1/3= 8 Days
8 day = time taken by B in completing 1/2 of work
B alone can complete the work = 16 days
The required time in completing the work if both A & B start working together?
16*24 / 40 = 48/5 Days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , GATE

2 3502
Q:

What are the 2 natural numbers, sum of whose squares is 52?

A) 2, 7 B) 3, 5
C) 4, 6 D) 5, 6
 
Answer & Explanation Answer: C) 4, 6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Square Roots and Cube Roots
Exam Prep: Bank Exams

3 3501
Q:

If the side of square is increased by 6%, then what will be the percentage increase in its area?

A) 3.2 B) 12.04
C) 12.12 D) 12.36
 
Answer & Explanation Answer: D) 12.36

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

2 3500
Q:

The costs of daily ticket of local train is Rs 160 and Monthly Pass costs Rs 2912. If I buy the Monthly Pass and travel for 26 days in a month then I save?

A) 25 percent B) 22 percent
C) 18 percent D) 30 percent
 
Answer & Explanation Answer: D) 30 percent

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

1 3500