Quantitative Aptitude - Arithmetic Ability Questions

Q:

Mandeep works 3 times as fast as Sampat. If Sampat can complete a job alone in 60 days, then in how many days can they together finish the job?

A) 7 days B) 4 days
C) 5 days D) 15 days
 
Answer & Explanation Answer: D) 15 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1729
Q:

Sumit is 28% less efficient than Amit. If Amit can make a wall in 54 days, then Sumit can complete the same work in how many days?

 

A) 75 B) 70
C) 72 D) 76
 
Answer & Explanation Answer: A) 75

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1728
Q:

In a class of 39 students there are 26 girls. The average weight of these girls is 42 Kgs and average weight of the full class is 48 kgs. What is the average weight (in kgs) of the boys of the class?

A) 54 B) 66
C) 60 D) 62
 
Answer & Explanation Answer: C) 60

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Average
Exam Prep: Bank Exams

3 1728
Q:

Rs. 490 is divided among A, B and C such that A's share is half that of B's and thrice that of C's. What is C's share?

A) Rs.49 B) Rs.147
C) Rs.294 D) Rs.245
 
Answer & Explanation Answer: A) Rs.49

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Partnership
Exam Prep: Bank Exams

1 1728
Q:

A watch having marked price as Rs 8400 is sold for Rs 5040 after two successive discounts. If the first discount is 25% then what is the second discount percentage?

A) 0.15 B) 0.2
C) 0.3 D) 0.25
 
Answer & Explanation Answer: B) 0.2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

0 1728
Q:

Two baskets together have 640 oranges. If (1/5)th of the oranges in the first basket be taken to the second basket. The number of oranges in the first basket is

A) 800 B) 600
C) 400 D) 300
 
Answer & Explanation Answer: C) 400

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

1 1727
Q:

X, Y and Z can do a piece of work in 30,40 and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?

A) 660/47 B) 640/47
C) 680/47 D) 665/47
 
Answer & Explanation Answer: A) 660/47

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams , CAT

1 1727
Q:

A can do 75% of a job in 9 days and B can do half of the job in 8 days. If they work on it together, then in how many days can they do half of the job?

A) 40/7 B) 24/7
C) 7/2 D) 9/2
 
Answer & Explanation Answer: B) 24/7

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1727