Quantitative Aptitude - Arithmetic Ability Questions

Q:

A contractor undertook to complete a piece of work in 120 Days and employed 140 men upon it. At the end of 66 days only half of the work was done,so he put on 25 extra men. By how much time did he exceed the specific time ?

A) 2 days B) 3 days
C) 4 days D) 5 days
 
Answer & Explanation Answer: A) 2 days

Explanation:

work done=total number of person x number of days;
half of work done = 140 x 66;
For half of remaining work 25 extra men are added.
Therefore, total men for half work remaining = 140 + 25 = 165;
Let 2nd half work will be completed in K days;
140 x 66 = 165 x K
K = 122;
Hence, extra days => 122-120 = 2days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

12 9847
Q:

A boat travels 72 km downstream in 8 hours and 84 km upstream in 12 hours. Find the speed of the boat in still water and the speed of the water current ?

A) 9 and 3 kmph B) 6 and 7 kmph
C) 8 and 1 kmph D) 7 and 2 kmph
 
Answer & Explanation Answer: C) 8 and 1 kmph

Explanation:

Downstream speed = 72km/8hrs  = 9 kmph
upstream speed = 84km/12hrs = 7 kmph
speed of boat = avg of downstream and upstream speeds
speed of boat = (9+7)/2kmph = 8 kmph.
current speed = half of the difference of downstream and upstream speeds
currend speed = (9-7)/2kmph = 1 kmph

Report Error

View Answer Report Error Discuss

Filed Under: Boats and Streams
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Bank PO

19 9836
Q:

If 35% of a number is 24 less than 50% of that number, then the number is ?

A) 80 B) 160
C) 100 D) 120
 
Answer & Explanation Answer: B) 160

Explanation:

Let the number be n. Then,

50% of n - 35% of n = 24

50/100 n - 35/100 n = 24

n = (24 x 100)/15 = 160.

Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

8 9835
Q:

If logxl+m-2n = logym+n-2l = logzn+l-2m, then xyz is equal to

A) 0 B) 1
C) lmn D) 2
 
Answer & Explanation Answer: B) 1

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Logarithms

95 9828
Q:

X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

A) 1/3 B) 2/3
C) 1/6 D) 5/6
 
Answer & Explanation Answer: C) 1/6

Explanation:

Given X can do in 10 days 

=> 1 day work of X = 1/10

 

Y can do in 15 days 

=> 1 day work of Y = 1/15

 

1day work of (X + Y) = 1/10 + 1/15 = 1/6

 

Given they are hired for 5 days

 => 5 days work of (X + Y) = 5 x 1/6 = 5/6

 Therefore, Unfinished work = 1 - 5/6 = 1/6 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

11 9821
Q:

Find the principal if the interest compounded at the rate of 10% per annum for two years is Rs. 420 ?

A) Rs. 2000 B) Rs. 2100
C) Rs. 1900 D) Rs. 2150
 
Answer & Explanation Answer: A) Rs. 2000

Explanation:

Given,
Compound rate, R = 10% per annum
Time = 2 years
C.I = Rs. 420
Let P be the required principal.
A = (P+C.I)
Amount, A = P1 + r100n

(P+C.I) = P1 + 101002

(P+420) = P[11/10][11/10]

P-1.21P = -420

0.21P = 420

Hence, P = 420/0.21 = Rs. 2000

Report Error

View Answer Report Error Discuss

Filed Under: Compound Interest
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

7 9815
Q:

Running 3/4th of his usual rate, a man is 15min late. Find his usual time in hours  ?

A) 2/3 hrs B) 3/4 hrs
C) 1/3 hrs D) 1/4 hrs
 
Answer & Explanation Answer: B) 3/4 hrs

Explanation:

Walking at 3/4th of usual rate implies that time taken would be 4/3th of the usual time. In other words, the time taken is 1/3rd more than his usual time

 

so 1/3rd of the usual time = 15min
or usual time = 3 x 15 = 45min = 45/60 hrs = 3/4 hrs.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Distance
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

5 9813
Q:

The interest on Rs.750 for 2yrs is the same as the True Discount on Rs.960 due 2yrs hence . If the rate of interest is same in both cases,it is:

A) 12% B) 14%
C) 15% D) 16
 
Answer & Explanation Answer: B) 14%

Explanation:

S.I on Rs.750= T.D on Rs. 960 

This means P.W of Rs. 960 due 2 years hence is Rs.750 

Therefore , T.D= Rs. (960 - 750) = Rs. 210 

Thus, S.I on Rs. 750 for 2 years is Rs. 210 

Rate =[ (100 x 210) / (750 x 2) ] % = 14%

Report Error

View Answer Report Error Discuss

Filed Under: True Discount

1 9810