Quantitative Aptitude - Arithmetic Ability Questions

Q:

What is the probability of getting a sum 9 from two throws of a dice?

A) 1/2 B) 3/4
C) 1/9 D) 2/9
 
Answer & Explanation Answer: C) 1/9

Explanation:

In two throws of a die, n(S) = (6 x 6) = 36.

Let E = event of getting a sum ={(3, 6), (4, 5), (5, 4), (6, 3)}.

P(E) =n(E)/n(S)=4/36=1/9.

Report Error

View Answer Report Error Discuss

Filed Under: Probability

80 51770
Q:

Find the next number in the number series?

1, 4, 12, 32, ?

A) 80 B) 100
C) 192 D) 169
 
Answer & Explanation Answer: A) 80

Explanation:

Next number of the sequence 1, 4, 12, 32,...

1 = 2 x 20

4 = 2 x 21

12 = 3 x 22

32 = 4 x 23

80 = 5 x 24.

Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO , IT Trainer

5 51664
Q:

35+37=?

 

A) 935 B) 612
C) 1135 D) 635
 
Answer & Explanation Answer: C) 1135

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

1 51657
Q:

If (x - 7)2 + (y + 10)2 + (z - 6)2 = 0, then find the value of x + y + z.

 

A) 1 B) 3
C) 5 D) 7
 
Answer & Explanation Answer: B) 3

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

1 51655
Q:

A,B,C together can do a piece of work in 10 days.All the three started workingat it together and after 4 days,A left.Then,B and C together completed the work in 10 more days.In how many days can complete a work alone ?

A) 25 B) 24
C) 23 D) 21
 
Answer & Explanation Answer: A) 25

Explanation:

(A+B+C) do 1 work in 10 days.

So (A+B+C)'s 1 day work=1/10 and as they work together for 4 days so workdone by them in 4 days=4/10=2/5


Remaining work=1-2/5=3/5

 

(B+C) take 10 more days to complete 3/5 work. So( B+C)'s 1 day work=3/50


Now A'S 1 day work=(A+B+C)'s 1 day work - (B+C)'s 1 day work=1/10-3/50=1/25

A does 1/25 work in in 1 day

Therefore 1 work in 25 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

125 51481
Q:

Find the odd man out of the number series?

18, 37, 76, 155, 314, 635

A) 37 B) 155
C) 314 D) 635
 
Answer & Explanation Answer: D) 635

Explanation:

Given Number series is 18     37     76     155     314     635

 

follows a pattern that, 

 

18

 

18 x 2 +1 = 37

 

37 x 2 +2 = 76

 

76 x 2 +3 = 155

 

155 x 2 +4 = 314

 

314 x 2 +5 = 633 not 635

 

 

 

Hence, the odd man is 635.

Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

7 51465
Q:

Given that (a2 + b2) = 60, then find the value of (a + b)2 + (a - b)2 ?

 

A) 90 B) 120
C) 140 D) 150
 
Answer & Explanation Answer: B) 120

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 51360
Q:

Solve the following :

 

196 - 19.6 - 1.96 - 0.196 = ?

 

A) 173.254 B) 173.234
C) 174.234 D) 174.244
 
Answer & Explanation Answer: D) 174.244

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 51360