Q:

Arun and Amit can do a piece of work in 9 days and 12 days respectively. If they work for alternate days and Amit starts the work first, then in how many days 35/36 parts of whole work will be completed?

A) 10 days B) 12 days
C) 5 days D) 8 days
 
Answer & Explanation Answer: A) 10 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

6 1582
Q:

An amount fetched a total simple interest of Rs. 3200 at the rate of 6.25 %/yr in 4 years. What is the amount (in Rs)?

A) 13800 B) 11800
C) 12800 D) 14800
 
Answer & Explanation Answer: C) 12800

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simple Interest
Exam Prep: Bank Exams

0 1582
Q:

In a triangle XYZ , which of the following conditions is true

A) XY ­ YZ > ZX B) XY + YZ < ZX
C) XY ­ YZ < XZ D) XY + ZX < YZ
 
Answer & Explanation Answer: C) XY ­ YZ < XZ

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Alligation or Mixture
Exam Prep: Bank Exams

2 1581
Q:

If 2x2+2y2=4a the find the value of 2ax2-a+2ay2-a

A) 0 B) 1
C) a D) 2a
 
Answer & Explanation Answer: A) 0

Explanation:
Report Error

View Answer Report Error Discuss

0 1581
Q:

The cube of 997 is

A) 991026973 B) 991029673
C) 991029773 D) 991097273
 
Answer & Explanation Answer: A) 991026973

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Square Roots and Cube Roots
Exam Prep: Bank Exams

1 1581
Q:

7/15 of 5/3 of a number is greater than 7/9 of 3/5 of the same number by 9. Find the quadruple of the number.

A) 115.72 B) 114.72
C) 113.72 D) 112.72
 
Answer & Explanation Answer: A) 115.72

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Problems on Numbers
Exam Prep: Bank Exams , CAT

0 1581
Q:

If two successive discounts of 30% and 10% are given, then what will be the ratio of marked price to selling price?

 

A) 50 : 21 B) 25 : 9
C) 100 : 63 D) 25 : 21
 
Answer & Explanation Answer: C) 100 : 63

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

0 1581
Q:

Product of 6ab, 3b and 4a is

A) 72a2b2 B) 144ab
C) 72ab D) 144a2b2
 
Answer & Explanation Answer: A) 72a2b2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 1581