Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

M is thrice as good as workman as N and together they finish a piece of work in 30 days. In how many days will M alone finish the work?

A) 50 B) 40
C) 60 D) 45
 
Answer & Explanation Answer: B) 40

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1311
Q:

Murad can do a piece of work in 33 hours. If he is joined by Joel who is 100% more efficient, in what time will they together finish the work?

A) 4 hours B) 6 hours
C) 2 hours D) 11 hours
 
Answer & Explanation Answer: D) 11 hours

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1299
Q:

Robin can do a work alone in 9 days. Amit can do the same work alone in 6 days. Both of them finish the work together and they get a total Rs 2500. What isthe share (in Rs) of Robin?

A) 1700 B) 1200
C) 1500 D) 1000
 
Answer & Explanation Answer: D) 1000

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

2 1285
Q:

A can paint a house in 45 days and B can do it in 15 days. Along with C, they did the job in 5 days only. Then, C alone can do the job in how many days?

A) 12 B) 9
C) 15 D) 8
 
Answer & Explanation Answer: B) 9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1263
Q:

A can do a work in 15 days and B in 9 days. If they work on it together for 5 days, then what fraction of work is left?

A) 1/6 B) 3/7
C) 1/3 D) 1/9
 
Answer & Explanation Answer: D) 1/9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1248
Q:

50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

A) 36 B) 38
C) 40 D) 45
 
Answer & Explanation Answer: C) 40

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , Bank Exams
Job Role: Bank PO , Bank Clerk

2 1245
Q:

Manish can complete a work in 21 days and Karan can complete the same work in 28 days. If both together work for 7 days, then what fraction of total work is left?

 

A) 3/5 B) 2/3
C) 7/12 D) 5/12
 
Answer & Explanation Answer: D) 5/12

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1239
Q:

Working alone A can do the task in 27 hours and B can do it in 54 hours. Find C's share (in Rs) if A, B and C get paid Rs 4,320 for completing a task in 12 hours on which they worked together.

A) 1440 B) 960
C) 1920 D) 1280
 
Answer & Explanation Answer: A) 1440

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1218