Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A can do a work in 8 days, B can do the same work in 10 days and C can do the same work in 12 days. If all three of them do the same work together and they are paid Rs 7400, then what is the share (in Rs) of B?

A) 2600 B) 3000
C) 2400 D) 2000
 
Answer & Explanation Answer: C) 2400

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1161
Q:

Amit can complete a work in 25 days and Punit can complete the same work in 20 days. Punit alone worked at it for 10 days and then left the work. In how many days will Amit alone complete the remaining work?

A) 10.5 B) 11.5
C) 12.5 D) 13.5
 
Answer & Explanation Answer: C) 12.5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1152
Q:

A  field  can  be  reaped  by  12  men  or  18  women  in  14  days.  In  how  many  days  can  8  men  and  16 women reap it?

A) 26 days B) 24 days
C) 9 days D) 8 days
 
Answer & Explanation Answer: C) 9 days

Explanation:
12 men or 18 women can complete in 14 days
8 men and 16 women can complete in how many days
12men = 18 women (Comparing efficiencies)
1men = 18/12 = 1.5 women
8 men and 16 women = 12women + 16 women = 28 women
18 women completes in 14 days
1 woman completes in 14*18 days
28 women completes in (14*18)/28 days = 9 days
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1150
Q:

P and Q can do a project in 150 and 100 days respectively. In how many days can they complete 60% of the project if they work together?

A) 12 days B) 72 days
C) 42 days D) 36 days
 
Answer & Explanation Answer: D) 36 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1141
Q:

A and B together do a job in 6.75 days and A could do the job in 9 days if he worked alone. How many days would B take to do the job if he worked alone?

A) 27 B) 18
C) 24 D) 21
 
Answer & Explanation Answer: A) 27

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1140
Q:

The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days.

A) 4 Days B) 3 Days
C) 2 Days D) 1 Day
 
Answer & Explanation Answer: D) 1 Day

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1140
Q:

If 10 people can do a job in 20 days,then 20 people with twice the efficiency can do the same job in

A) 5 days B) 10 days
C) 20 days D) 40 days
 
Answer & Explanation Answer: A) 5 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1139
Q:

If A, B and C together do a job in 4 days, A and C together do the job in 4.5 days and B and C together do the job in 12 days then in how many days can C alone do the job?

A) 36 B) 6
C) 18 D) 12
 
Answer & Explanation Answer: C) 18

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work