Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A can do a work in 15 days and B in 9 days. If they work on it together for 5 days, then what fraction of work is left?

A) 1/6 B) 3/7
C) 1/3 D) 1/9
 
Answer & Explanation Answer: D) 1/9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 2411
Q:

One tap can fill a water tank in 50 mins and another tap can make the filled tank empty in 75 mins. If both the taps are open together, already half filled tank would be full in

A) 60 min B) 75 min
C) 125 min D) 150 min
 
Answer & Explanation Answer: B) 75 min

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 2397
Q:

A and B together can do a piece of work in 9 days. If A does thrice the work of B in a given time, the time A alone will take to finish the work is

A) 4 days B) 6 days
C) 8 days D) 12 days
 
Answer & Explanation Answer: D) 12 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

6 2392
Q:

45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?

A) 23 B) 45
C) 30 D) 25
 
Answer & Explanation Answer: C) 30

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2386
Q:

P and Q can do a project in 6 and 12 days respectively. In how many days can they complete 25% of the project if they work together?

A) 2 days B) 4 days
C) 1 days D) 8 days
 
Answer & Explanation Answer: C) 1 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 2377
Q:

X can complete 5/7 part of a work in 10 days and Y can complete 3/4 part of the same work in 9 days. In how many days will both complete 13/21 part  of the total work?

 

A)  6 B) 4
C) 3 D) 12
 
Answer & Explanation Answer: B) 4

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

9 2375
Q:

A can do a work in 8 days, B can do the same work in 10 days and C can do the same work in 12 days. If all three of them do the same work together and they are paid Rs 7400, then what is the share (in Rs) of B?

A) 2600 B) 3000
C) 2400 D) 2000
 
Answer & Explanation Answer: C) 2400

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2365
Q:

50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

A) 36 B) 38
C) 40 D) 45
 
Answer & Explanation Answer: C) 40

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , Bank Exams
Job Role: Bank PO , Bank Clerk

3 2337