Verify Scope is the process of

A) progressively elaborating and documenting the project work that produces the product of the project. B) subdividing the major product deliverables into smaller, more manageable components.
C) obtaining formal acceptance of the project scope by the stakeholders. D) influencing the factors that create scope changes to ensure that changes are agreed upon, determining that a scope change has occurred and managing the changes when and if they occur.
 
Answer & Explanation Answer: C) obtaining formal acceptance of the project scope by the stakeholders.

Explanation:

“Verify Scope is the process of formalizing acceptance of the completed project deliverables. Verifying scope includes reviewing deliverables with the customer or sponsor to ensure that they are completed satisfactorily and obtaining formal acceptance of deliverables by the customer or sponsor.” PMBOK [5.4]

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 3230
Q:

Project Integration Management

What are the Project Management Processes included in the Project Integration Management?

Answer

The Integrative Project Management Processes include:


Develop Project Charter - Developing the project charter that formally authorizes a project or a project Phase.


Develope Preliminary Project Scope Statement - Developing the preliminary project scope statement that provides a high level scope narrative


Develop Project Management Plan -  Documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans into a project management plan.


Direct and Manage Project Execution- Executing the work defined in the project management plan to achieve the project's requirements defined in the project scope statement.


Monitor and Control Project Work - Monitoring and controlling the processes used to initiate, plan, execute, and close a project to meet the performance objectives defined in the project management plan.


Integrated Change Control - Reviewing all change requests, approving changes, and controlling changes to the deliverables and organizational process assets.


Close Project - Finalizing all activities across all of the Project Management Process Groups to formally close the project or a Project phase.

Report Error

View answer Workspace Report Error Discuss

0 3229
Q:

Infection of salivary glands by a virus leads to 

A) tetanus B) mumps
C) pyorrhoea D) ulcers
 
Answer & Explanation Answer: B) mumps

Explanation:

Mumps : This is a swelling caused by information of parotid glands placed in front of our ear region. The inflammation is caused by a virus.

Report Error

View Answer Report Error Discuss

Filed Under: Biology

3 3229
Q:

What is Bandwidth?

Answer

Every line has an upper limit and a lower limit on the frequency of signals it can carry. This limited range is called the bandwidth

Report Error

View answer Workspace Report Error Discuss

Subject: Networking
Job Role: Network Engineer

1 3229
Q:

Higher Quality Scores typically result in

A) faster delivery of daily budget B) higher costs and lower ad positions
C) lower costs and better ad positions D) less overall impressions
 
Answer & Explanation Answer: C) lower costs and better ad positions

Explanation:

Higher Quality Scores typically result in lower costs and better ad positions. Quality Score is Google's rating of the quality and relevance of both your keywords and PPC ads. It is used to determine your cost per click (CPC) and multiplied by your maximum bid to determine your ad rank in the ad auction process.

Report Error

View Answer Report Error Discuss

Filed Under: Advertising and Media
Job Role: Analyst , IT Trainer

4 3228
Q:

I can grow quickly and I can die slowly, I can be a terrible pain or a comfort and joy. You never find me all by myself. What am I?

Answer

A relationship.

Report Error

View answer Workspace Report Error Discuss

Subject: Word Puzzles Exam Prep: Bank Exams
Job Role: Bank Clerk

7 3228
Q:

The physical components of a computer are referred to as

A) Processor B) Software
C) Hardware D) Input devices
 
Answer & Explanation Answer: C) Hardware

Explanation:

The physical components of a computer are referred to as Hardware of the computer. 

 

The hardware components of the computer includes :

  • Processor.
  • Main memory.
  • Secondary memory.
  • Input devices.
  • Output devices.
Report Error

View Answer Report Error Discuss

Filed Under: Computer
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 3228
Q:

Which position is always staffed in ICS applications?

A) Commander in Chief B) Incident Commander
C) Operations Section Chief D) None of the above
 
Answer & Explanation Answer: B) Incident Commander

Explanation:

The Incident Commander is the only position that is always staffed in ICS applications. On small incidents and events, one person, the Incident Commander, may accomplish all five management functions.

The Incident Command System (ICS) is a standardized approach to the command, control, and coordination of emergency response providing a common hierarchy within which responders from multiple agencies can be effective.

Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

0 3228