Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A can do 75% of a job in 9 days and B can do half of the job in 8 days. If they work on it together, then in how many days can they do half of the job?

A) 40/7 B) 24/7
C) 7/2 D) 9/2
 
Answer & Explanation Answer: B) 24/7

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1142
Q:

A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a day?

A) 59/11 B) 48/11
C) 70/11 D) 65/11
 
Answer & Explanation Answer: B) 48/11

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1138
Q:

Akash is 3 times as good a workman as Baldev and therefore is able to finish a job in 40 days less than Baldev. Working together, they can finish it in _____.

A) 15 days B) 60 days
C) 20 days D) 10 days
 
Answer & Explanation Answer: A) 15 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1138
Q:

P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together?

A) 9 days B) 27 days
C) 36 days D) 18 days
 
Answer & Explanation Answer: D) 18 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1137
Q:

Azhar is 4 times as good a workman as Balaraj and therefore is able to finish a job in 45 days less than Balaraj. Working together, they can do it in:

A) 6 days B) 18 days
C) 24 days D) 12 days
 
Answer & Explanation Answer: D) 12 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1128
Q:

A piece of work was finished by A, B and C together. A and B together finished 60% of the work and B and C together finished 70% of the work. Who among the three is most efficient?

A) A B) B
C) C D) None
 
Answer & Explanation Answer: C) C

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1118
Q:

Painter 'A' can paint a house in 10 days and 'B' can do it in 20 days. With help of 'C', they did the job in 5 days only. Then, 'C' alone can do the job in:

A) 20 days B) 10 days
C) 40 days D) 50 days
 
Answer & Explanation Answer: A) 20 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1116
Q:

A can do a work in 21 days and B in 42 days. If they work on it together for 7 days, then what fraction of work is left?

A) 1/3 B) 1/4
C) 2/3 D) 1/2
 
Answer & Explanation Answer: D) 1/2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1108