FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A Contractor employed a certain number of workers  to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the  scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?

A) 10 % B) 14 ( 2/7 )%
C) 20 % D) Can't be determined
 
Answer & Explanation Answer: B) 14 ( 2/7 )%

Explanation:

Let he initially employed x workers which works for D days and he estimated 100 days for the whole work and then he doubled the worker for (100-D) days.

D * x +(100- D) * 2x= 175x 

=>  D= 25 days 

Now , the work done in 25 days = 25x 

Total work = 175x

Therefore, workdone before increasing the no of workers = 25x175x×100 % = 1427%

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

107 31616
Q:

A and B can do a piece of work in 40 and 50 days. If they work at it an alternate days with A beginning in how many days, the work will be finished ?

Answer

(A+B)'s two days work = 140+150=9200 


 


Evidently, the work done by A and B duing 22 pairs of days 


 


 i.e in 44 days = 22×9200=198200 


 


Remaining work = 1-198200= 1/100


 


 Now on 45th day A will have the turn to do 1/100 of the work and this work A will do in 40×1100=25


 


 Therefore,  Total time taken = 4425daya

Report Error

View answer Workspace Report Error Discuss

Subject: Time and Work
Job Role: Bank PO

72 28832
Q:

A and B together can do a piece of work in 40 days. A having worked for 20 days, B finishes the remaining work alone in 60 days. In How many days shall B finish the  whole work alone?

A) 60 B) 70
C) 80 D) 90
 
Answer & Explanation Answer: C) 80

Explanation:

Let A's 1 day's work=x and B's 1 day's work=y

Then x+y = 1/40 and 20x+60y=1 

Solving these two equations , we get : x= 1/80 and y= 1/80

Therefore B's  1 day work = 1/80

Hence,B alone shall finish the whole work in 80 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

34 28258
Q:

A is thrice efficient as B and C is twice as efficient as B. what is the ratio of number of days taken by A,B and C, when they work individually?

A) 2:6:3 B) 2:3:6
C) 1:2:3 D) 3:1:2
 
Answer & Explanation Answer: A) 2:6:3

Explanation:

                                                A    :    B    :    C   

Ratio of efficiency               3     :    1    :    2   

Ratio of No.of days            1/3  :   1/1  :   1/2    

     or                                       2    :    6    :    3   

Hence A is correct.  

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

45 27950
Q:

9 men and 12 boys finish a job in 12 days, 12 men and 12 boys finish it in 10 days. 10 men and 10 boys shall finish it in how many days ?

A) 15 days B) 11 days
C) 14 days D) 12 days
 
Answer & Explanation Answer: D) 12 days

Explanation:

9M + 12B ----- 12 days ...........(1)
12M + 12B ------- 10 days........(2)
10M + 10B -------?
108M + 144B = 120M +120B
24B = 12M => 1M = 2B............(3)

From (1) & (3)

18B + 12B = 30B ---- 12 days

20B + 10B = 30B -----? => 12 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

22 26404
Q:

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days  ?

A) 9 days B) 11 days
C) 13 days D) 15 days
 
Answer & Explanation Answer: C) 13 days

Explanation:

Ratio of times taken by A and B = 100 : 130 = 10 : 13.
Suppose B takes x days to do the work.

Then, 10 : 13 :: 23 : x     =>     x = ( 23 x 13/10 )     =>     x = 299 /10.

A's 1 day's work = 1/23 ;
B's 1 day's work = 10/299 .

(A + B)'s 1 day's work = ( 1/23 + 10/299 ) = 23/299 = 113 .

Therefore, A and B together can complete the work in 13 days. 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

52 26201
Q:

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days what is time taken by 15 men and 20 boys?

A) 4 days B) 6 days
C) 7 days D) 5 days
 
Answer & Explanation Answer: A) 4 days

Explanation:

Given that 

6 men and 8 boys can do a piece of work in 10 days 

26 men and 48 boys can do the same in 2 days

 

As the work done is equal,

10(6M + 8B) = 2(26M + 48B)

60M + 80B = 52M + 96B

=> M = 2B

=> B = M/2 ……(1)

 

Now Put (1) in 15M + 20B

=> 15M + 10M = 25M

Now, 6M + 8B in 10 days

=> (6M + 4M) 10 = 100M

Then D(25M) = 100M

=> D = 4 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

33 26095
Q:

A does half as much work as Band C does half as much work as A and B together. If C alone can finish the work in 40 days, then together ,all will finish the work in  ?

A) 17 + 4/7 days B) 13 + 1/3 days
C) 15 + 3/2 days D) 16 days
 
Answer & Explanation Answer: B) 13 + 1/3 days

Explanation:

C alone can finish the work in 40 days.
As given C does half as much work as A and B together
=> (A + B) can do it in 20 days
(A + B)s 1 days wok = 1/20.
A's 1 days work : B's 1 days Work = 1/2 : 1 = 1:2(given)
A's 1 day’s work = (1/20) x (1/3) = (1/60) [Divide 1/20 in the raio 1:2]
B's 1 days work = (1/20) x (2/3) = 1/30
(A+B+C)'s 1 day's work = (1/60) + (1/30) + (1/40) = 9/120 = 3/40

All the three together will finish it in 40/3 = 13 and 1/3 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Bank Clerk , Bank PO

47 25302