Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Pradeep has done 1/4th of a job in 14 days, Saquib completes the rest of the job in 56 days. In how many days can they together complete the job?

A) 64 days B) 32 days
C) 16 days D) 8 days
 
Answer & Explanation Answer: B) 32 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1702
Q:

Five women can do a work in 36 days. If the ratio between the capacity of a man and a woman is 3:1, then find how many days it will take 5 men to complete the same woek?

A) 12 days B) 15 days
C) 18 days D) 108 days
 
Answer & Explanation Answer: A) 12 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1693
Q:

A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?

A) 12.5 days B) 100 days
C) 22.5 days D) 35 days
 
Answer & Explanation Answer: B) 100 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1690
Q:

Akash is 3 times as good a workman as Baldev and therefore is able to finish a job in 40 days less than Baldev. Working together, they can finish it in _____.

A) 15 days B) 60 days
C) 20 days D) 10 days
 
Answer & Explanation Answer: A) 15 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1678
Q:

A does 30% of a work in 30 days. He then calls in B and they together finish the remaining work in 20 days. How long B alone would take to do the whole work?

A) 40 days B) 80 days
C) 120 days D) 20 days
 
Answer & Explanation Answer: A) 40 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1676
Q:

A,B and C contract a work for Rs. 440. Together A and B are to do 9/11 of the work. The share of C should be:

A) 75 B) 90
C) 100 D) 80
 
Answer & Explanation Answer: D) 80

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1657
Q:

Ehsaan is twice as good a worker as Kamal and together they finish a piece of work in 29 days. In how many days will Kamal, working alone, finish the work?

A) 58 B) 70
C) 87 D) 116
 
Answer & Explanation Answer: C) 87

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1652
Q:

P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together?

A) 9 days B) 27 days
C) 36 days D) 18 days
 
Answer & Explanation Answer: D) 18 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1652