Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A  field  can  be  reaped  by  12  men  or  18  women  in  14  days.  In  how  many  days  can  8  men  and  16 women reap it?

A) 26 days B) 24 days
C) 9 days D) 8 days
 
Answer & Explanation Answer: C) 9 days

Explanation:
12 men or 18 women can complete in 14 days
8 men and 16 women can complete in how many days
12men = 18 women (Comparing efficiencies)
1men = 18/12 = 1.5 women
8 men and 16 women = 12women + 16 women = 28 women
18 women completes in 14 days
1 woman completes in 14*18 days
28 women completes in (14*18)/28 days = 9 days
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1621
Q:

Ram and Shyam undertook a work for Rs 5600. Ram alone can do the work in 5 days and Shyam alone can do the work in 9 days. If they worktogether, then what will be the difference (in Rs.) in the amount they receive?

A) 1800 B) 2400
C) 1600 D) 2200
 
Answer & Explanation Answer: C) 1600

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

6 1602
Q:

A painter can paint a fence in 24 hours. After 6 hours he takes a break. What fraction of the fence is yet to be painted?

A) 0.6 B) 0.2
C) 0.75 D) 0.8
 
Answer & Explanation Answer: C) 0.75

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1599
Q:

Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?

A) 3/5 B) 1/3
C) 1/2 D) 2/5
 
Answer & Explanation Answer: D) 2/5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 1597
Q:

P alone can do a piece of work in 8 days and Q alone can do the same work in 10 days. In how many days will both together complete the same work?

A) 40/9 B) 20/9
C) 60/7 D) 40/7
 
Answer & Explanation Answer: A) 40/9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1593
Q:

A and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest work in 14 days. A alone can complete the work in _____.

A) 24 days B) 22 days
C) 20 days D) 18 days
 
Answer & Explanation Answer: A) 24 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1592
Q:

S does half as much work as T in 1/7 of the time taken by T. If together they take 21 days to complete a work, then how may days shall S take to complete that work alone?

 

 

A) 26   B)  27  
C) 28   D) 32
 
Answer & Explanation Answer: B)  27  

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1592
Q:

A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is

A) 20 days B) 21 days
C) 22 days D) 24 days
 
Answer & Explanation Answer: D) 24 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work