Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A can do a work in 15 days and B in 20 days. If they work on it together for 6 days, then what fraction of work is left?

A) 1/4 B) 2/9
C) 1/5 D) 3/10
 
Answer & Explanation Answer: D) 3/10

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1045
Q:

30 men working 5 hours a day can do a task in 16 days. In how many days will 40 men working 6 hours a day do the same task?

A) 12 days B) 10 days
C) 15 days D) 18 days
 
Answer & Explanation Answer: B) 10 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1045
Q:

P and Q undertook to do a work for Rs 7200. P alone could do it in 20 days and Q alone in 12 days. With the assistance of R they finished the work in 5days. What is the share (in Rs) of R?

 

A) 1800   B) 2400  
C) 2800   D) 2600
 
Answer & Explanation Answer: B) 2400  

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1044
Q:

If 7 spiders make 7 webs in 7 days , then 1 spider will make 1 web in how many days ?

A) 1 B) 7/2
C) 7 D) 49
 
Answer & Explanation Answer: C) 7

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1041
Q:

Atul and Binay together complete a piece of work in 5 days. If Binay alone can complete the same work in 8 days, how many days Atul take to complete the same work alone?

A) 40/3 days B) 20/3 days
C) 9 days D) 10 days
 
Answer & Explanation Answer: A) 40/3 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1039
Q:

Some girls can do a piece of work in 18 days. In how much time (in days) two times the number of such girls will complete thrice of the work?

 

A) 12 B) 27
C) 21 D) 24
 
Answer & Explanation Answer: B) 27

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1021
Q:

P can do a piece of work in 60 days & Q can do the same work in 50 days. Find the ratio of working efficiencies of P to Q.

 

A) 1/3 B) 6/5
C) 5/6 D) 4/5
 
Answer & Explanation Answer: C) 5/6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 994
Q:

Ram is thrice as fast as Mohan and Nohan is twice as fast as Sohan. The distance covered by Sohan in 42 minutes will be covered by Mohan in

 

A) 18 min B) 21 min
C) 20 min D) 22 min
 
Answer & Explanation Answer: B) 21 min

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 984