Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

After working for 8 days, Hari Ram finds that only 1/3 rd of the work has been done. He employs Satya who is 60% as efficient as Hari Ram. How many days more would Satya take to complete the work ?

A) 24 1/2 days B) 25 3/2 days
C) 24 2/3 days D) 26 2/3 days
 
Answer & Explanation Answer: D) 26 2/3 days

Explanation:

1/3 ---- 8

1 -------?
Hari can do total work in = 24 days

As satya is 60% efficient as Hari, then

Satya = 1/24 x 60/100 = 1/40

=> Satya can do total work in 40 days

1 ----- 40

2/3 ---- ? => 26 2/3 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

11 6202
Q:

A can finish a work in 15 days and B can do the same work in 12 days . B worked for 8 days and left the job .In how many days, A alone can finish the remaining work?

A) 6 days B) 5 days
C) 4 days D) 3 days
 
Answer & Explanation Answer: B) 5 days

Explanation:

B's 8 days work=(1/12) x 8 = 2/3

Reaining work= 1/3

Now, 1/15 work is done by A in 1 day

Therefore, 1/3 work is done by A in 15 x (1/3) = 5 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

11 12471
Q:

P can do a piece of work in 5 less days than Q. If both of them can do the same work in 1119days, in how many days will Q alone do the same work  ?

A) 24 days B) 25 days
C) 20 days D) 19 days
 
Answer & Explanation Answer: B) 25 days

Explanation:

Let Q complete that work in 'L' days

 

=> 1L + 1L-5 = 9100

 

=> 9L2-245L+500=0

 

L = 25 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

11 4218
Q:

Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work ?

A) 3 days B) 2 days
C) 6 days D) 12 days
 
Answer & Explanation Answer: C) 6 days

Explanation:

From the given data,

12 children 16 days work,
One child’s one day work = 1/192.


8 adults 12 days work,
One adult’s one day’s work = 1/96.


Work done in 3 days = ((1/96) x 16 x 3) = 1/2


Remaining work = 1 – 1/2 = 1/2


(6 adults+ 4 children)’s 1 day’s work = 6/96 + 4/192 = 1/12

1/12 work is done by them in 1 day.

1/2 work is done by them in 12 x (1/2) = 6 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: TOEFL , GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

11 11832
Q:

If a soldier fires 7 shots from a gun in 12 minutes then find the total number of shots fired by the man in 3/2 hrs.

A) 45 B) 44
C) 46 D) 47
 
Answer & Explanation Answer: C) 46

Explanation:

Here given soldier shots 7 shots in 12 min

=> 1 shot doen't take any time in 12 min 

=> Only 6 shots take 12 min 

12 min ------ 6 shots 

90 min ------ ? shots 

=> 90 x (6/12) = 45 

Therefore, total shots fired in 90 minutes = 45 + 1 = 46 shots.

Report Error

View Answer Report Error Discuss

10 5784
Q:

A garrison of 2000 men has provisions for 54 days. At the end of 15 days, a reinforcement arrives, and it is now found that the provisions will last only for 20 days more. What is the reinforcement ?

A) 1900 B) 2100
C) 1700 D) 2000
 
Answer & Explanation Answer: A) 1900

Explanation:

Given 2000 ---- 54 days

The provisions for 2000 men for 39 days can be completed by 'm' men for only 20 days.

i.e, 2000 ----- 39 days == m ---- 20 days

=> m x 20 = 2000 x 39

m = 3900

So total men for 20 days is 3900

=> 2000 old and 1900 new reinforcement.

Hence, reinforcement = 1900.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

10 12835
Q:

A,B,C can complete a work in 15,20 and 30 respectively.They all work together for two days then A leave the work,B and C work some days and B leaves 2 days before completion of that work.how many days required to complete the whole work?

Answer

Given A,B,C can complete a work in 15,20 and 30 respectively.


The total work is given by the LCM of 15, 20, 30 i.e, 60.


A's 1 day work = 60/15 = 4 units


B's 1 day work = 60/20 = 3 units


C's 1 day work = 60/30 = 2 units


(A + B + C) worked for 2 days = (4 + 3 + 2) 2 = 18 units


 Let B + C worked for x days = (3 + 2) x = 5x units


C worked for 2 days = 2 x 2 = 4 units


Then, 18 + 5x + 4 = 60


22 + 5x = 60


5x = 38


x = 7.6


 


Therefore, total number of days taken to complete the work = 2 + 7.6 + 2 = 11.6 = 11 3/5 days.

Report Error

View answer Workspace Report Error Discuss

Subject: Time and Work Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

10 3496
Q:

In a hostel, there was food for 1000 students for one month. After 10 days, 1000 more students joined the hostel. How long would the students be able to carry on with the remaining food?

A) 10 days B) 15 days
C) 20 days D) 5 days
 
Answer & Explanation Answer: A) 10 days

Explanation:

After 10 days, the remaining food would be sufficient for the 1000 students for 20 more days

-->If 1000 more students are added, it shall be sufficient for only 10 days (as the no. of students is doubled, the days are halved).

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams
Job Role: Bank PO , Bank Clerk

10 7182