Q:
         
         
            
               Relation Between Efficiencies
            
                           
                  
6 boys and 8 girls finish a job in 6 days and 14 boys and 10 girls finish the same job in 4 days. In how many days working together 1 boy and 1 girl can finish the work?
               
                      
         
             Answer
                        Sol : In this kind of questions we find the work force required to complete the work in 1 day (or given unit of time) then we equate the work force to find the relationship between the efficiencies (or work rate) between the different workers.
 
Therefore, 6B+8G = 6 days
 => 6(6B+8G)= 1 day  (inversely proportional)
 => 36B+48G =1         ( by unitary method)
 
Again  14B+10G = 4days
 => 56B+40G =1
 
so, here it is clear that either we employ 36B and 48G to finish the work in 1 day or 56B and 40G to finish the same job in 1 day. thus , we can say
 => 36B+48G = 56B+40G
 => G= 2.5B
Thus a Girl is 2.5 times as efficient as a boy.
 
Now, since  36B+48G = 1
 => 36B+48(2.5 B)=1
 =>156B=1
i.e., to finish the job in 1 day 156 boys are required or the amount of work is 156 boys-days
 
Again    1G+1B=2.5B+1B=3.5B
 
Now, since 156 boys can finish the job in 1 day
so 1 boy can finish the job in 156 days
Therefore, 3.5 boys can finish the job in  days.
 
 
          
         
         
         