Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Raman can do a work in 5 days, Jatin can do the same work in 7 days and Sachin can do the same work in 9 days. If they do the same work together and they are paid Rs 2860, then what is the share (in Rs) of Raman?

A) 1260 B) 700
C) 900 D) 870
 
Answer & Explanation Answer: A) 1260

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT

4 1037
Q:

If 10 people can do a job in 20 days,then 20 people with twice the efficiency can do the same job in

A) 5 days B) 10 days
C) 20 days D) 40 days
 
Answer & Explanation Answer: A) 5 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1140
Q:

In a regular week, there are 5 working days and for each day, the working hours are 8. A man gets Rs. 2.40 per hour for regular work and Rs. 3.20 per hours for overtime. If he earns Rs. 432 in 4 weeks, then how many hours does he work for ?

A) 145 B) 165
C) 175 D) 135
 
Answer & Explanation Answer: C) 175

Explanation:

Given that,

 working days = 5

 working hours = 8

 A man get rupess per hour is Rs.2.40

 So in one day the man get total rupees is 2.40 x 8 = 19.2

 So in 5 days week the man get total rupees is 19.2 x 5 = 96

 So in 4 week the man get total rupees is 96 x 4 = 384

 So the man worked for = 160hours in 4 weeks

 

 But given that the man earned Rs.432

 

 Hence remaning money is (432-384 = 48)which is earn by doing overtime work

 


Overtime hours  = 48/3.20 = 15


So total worked hours is = 15 + 160 = 175.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

4 3872
Q:

A can do a work in 20 days and B in 50 days. If they work on it together for 5 days, then what fraction of work is left?

A) 13/20 B) 1/3
C) 1/6 D) 2/9
 
Answer & Explanation Answer: A) 13/20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1046
Q:

A can do a piece of work in 21 days and B in 28 days. Together they started the work and B left after 4 days. In how many days can A alone do the remaining work ?

A) 14 days B) 18 days
C) 21 deays D) 16 days
 
Answer & Explanation Answer: A) 14 days

Explanation:

Let A worked for x days.

x/21 + 4/28 = 1  => x = 18

 

A worked for 18 days. So, A can complete the remaining work in 18 - 4 = 14 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

4 10522
Q:

A work which could be finished in 11 days was finished 4 days earlier after 4 more men joined. The number of men employed was ?

A) 7 B) 8
C) 9 D) 10
 
Answer & Explanation Answer: A) 7

Explanation:

As the work is same
M1D1 = M2D2

Here Let the number of men employed was M
=> 11M = 7(M+4)
=> 11M - 7M = 28
=> M = 7

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

4 4463
Q:

A can make a cupboard in 10 days and B can do it in 50 days. Along with C, they did the job in 6.25 days only. Then in how many days C alone can do the job?

A) 20 B) 25
C) 16 D) 15
 
Answer & Explanation Answer: B) 25

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 761
Q:

A can do a work in 15 days and B in 9 days. If they work on it together for 5 days, then what fraction of work is left?

A) 1/6 B) 3/7
C) 1/3 D) 1/9
 
Answer & Explanation Answer: D) 1/9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1249